Microsoft Exam Questions

Which three actions should you perform in sequence?

DRAG DROP
You have a server that runs Windows Server 2012 R2.
You need to create a volume that will remain online if two disks in the volume fail. The solution must
minimize the number of disks used to create the volume.
Which three actions should you perform in sequence? (To answer, move the appropriate three
actions from the list of actions to the answer area and arrange them in the correct order.)

Answer: See the explanation

Explanation:
Explanation/Reference
Box 1: Add five physical disks.
Box 2: Create a storage space by using the default disk allocation.
Box 3: Create a virtual disk.