Which three actions should you perform?

Your company uses Project Standard 2013 to track project progress. You need to accurately calculate
cost performance index (CPI) as a health indicator. Which three actions should you perform? (Each
correct answer presents part of the solution. Choose three.)

A.
Ensure there is a value in the Status Date field.

B.
Ensure there is a value in the Standard Rate field.

C.
Ensure Task Dependencies exist in the schedule.

D.
Enter actual progress information.

E.
Level resources within available slack.