Which tasks are on the critical path? seenagape 14 years ago In Microsoft Office Project Standard 2007, you create the following project plan: You need to identify the critical path. Which tasks are on the critical path? A.1, 2, and 3 B.1, 2, 3, and 5 C.1, 3, 4, and 5 D.1, 2, 3, 4, and 5 ← Previous question Next question →