Which command should you use? seenagape 10 years ago You use bottom-up scheduling. You need to group four consecutive tasks in a major phase.You highlight the four tasks. Which command should you use? A. Outdent B. Fill Down C. Insert Summary D. Move Task Explanation: ← Previous question Next question →