What should you install on Server6?

###BeginCaseStudy###
Case Study: 1
Trey research
Scenario
Trey Research is a consulting company.
Trey Research has three offices. The offices are located in Seattle, Los Angeles, and Toronto.
Trey Research has two data centers. The data centers are located in Los Angeles and Toronto.
Existing Environment
The network contains a single-domain Active Directory forest named treyresearch.com. The network
contains switches that support either SNMPv1 or SNMPv2.
The forest contains 100 physical servers that run Windows Server 2008 R2 Service Pack 1 (SP1).
The relevant servers are configured as shown in the following table.

All of the System Center 2012 servers use Servers as a database server.
All of the VMM components in the production environment are installed on Server1. Server1 is
located in the Los Angeles data center.
Ten virtual machine hosts are located in the Toronto data center and 90 virtual machine hosts are
located in the Los Angeles data center.
Server9 is used to manage three virtualization hosts in a lab environment.
Requirements
Planned Changes
Trey Research plans to implement the following changes:
• Upgrade Servers to VMM 2012.
• Discover and monitor network switches by using Operations Manager.
• Grant the network technicians the required permissions to configure the network fabric.
• Install a System Center 2012 Service Manager management server on Server7 and a Service
Manager data warehouse management server on Servers.
• Provide external access to the Virtual Machine Manager Self-Service Portal (VMMSSP) by
using the names ssp.treyresearch.com and vmm.treyresearch.com.
Private Cloud Infrastructure Requirements
Trey Research identifies the following requirements for the private cloud infrastructure:
• Integrate VMM 2012 and Operations Manager 2012.
• Ensure that all VMM 2012 components are highly available.
• Ensure that virtual machines use a MAC address from a custom MAC address pool.
• Ensure that Hyper-V hosts can be deployed to bare-metal computers from Server6.
• Control the placement of virtual machines based on the performance data gathered by
Operations Manager.
Private Cloud Compliance Requirements
Trey Research identifies the following requirements for compliance in the private cloud
infrastructure:
• Ensure that updates on the Hyper-V hosts can be remediated.
• Generate the compliance status of all the servers in the fabric.
• Ensure that update baselines for all of the servers in the fabric are created.
Private Cloud Services Requirements
Trey Research identifies the following requirements for managing services in the private cloud:
• Users in the human resources department must be able to create virtual machines that have
two CPUs and 4 GB RAM by using the VMMSSP.

• Users in the marketing department must be able to create new virtual machines that will be
hosted in the Toronto office. The virtual machine templates for the marketing department users
must be stored in the Toronto office.

###EndCaseStudy###

You need to deploy Hyper-V hosts to meet the requirements for the private cloud infrastructure.
What should you install on Server6?

You need to prepare the environment to support the placement of virtual machines based on the performance of t

###BeginCaseStudy###
Case Study: 1
Trey research
Scenario
Trey Research is a consulting company.
Trey Research has three offices. The offices are located in Seattle, Los Angeles, and Toronto.
Trey Research has two data centers. The data centers are located in Los Angeles and Toronto.
Existing Environment
The network contains a single-domain Active Directory forest named treyresearch.com. The network
contains switches that support either SNMPv1 or SNMPv2.
The forest contains 100 physical servers that run Windows Server 2008 R2 Service Pack 1 (SP1).
The relevant servers are configured as shown in the following table.

All of the System Center 2012 servers use Servers as a database server.
All of the VMM components in the production environment are installed on Server1. Server1 is
located in the Los Angeles data center.
Ten virtual machine hosts are located in the Toronto data center and 90 virtual machine hosts are
located in the Los Angeles data center.
Server9 is used to manage three virtualization hosts in a lab environment.
Requirements
Planned Changes
Trey Research plans to implement the following changes:
• Upgrade Servers to VMM 2012.
• Discover and monitor network switches by using Operations Manager.
• Grant the network technicians the required permissions to configure the network fabric.
• Install a System Center 2012 Service Manager management server on Server7 and a Service
Manager data warehouse management server on Servers.
• Provide external access to the Virtual Machine Manager Self-Service Portal (VMMSSP) by
using the names ssp.treyresearch.com and vmm.treyresearch.com.
Private Cloud Infrastructure Requirements
Trey Research identifies the following requirements for the private cloud infrastructure:
• Integrate VMM 2012 and Operations Manager 2012.
• Ensure that all VMM 2012 components are highly available.
• Ensure that virtual machines use a MAC address from a custom MAC address pool.
• Ensure that Hyper-V hosts can be deployed to bare-metal computers from Server6.
• Control the placement of virtual machines based on the performance data gathered by
Operations Manager.
Private Cloud Compliance Requirements
Trey Research identifies the following requirements for compliance in the private cloud
infrastructure:
• Ensure that updates on the Hyper-V hosts can be remediated.
• Generate the compliance status of all the servers in the fabric.
• Ensure that update baselines for all of the servers in the fabric are created.
Private Cloud Services Requirements
Trey Research identifies the following requirements for managing services in the private cloud:
• Users in the human resources department must be able to create virtual machines that have
two CPUs and 4 GB RAM by using the VMMSSP.

• Users in the marketing department must be able to create new virtual machines that will be
hosted in the Toronto office. The virtual machine templates for the marketing department users
must be stored in the Toronto office.

###EndCaseStudy###

HOTSPOT
You need to prepare the environment to support the placement of virtual machines based on the
performance of the hosts. The solution must meet the requirements for the private cloud
infrastructure. What should you do on each server before you configure the connection between
VMM 2012 and Operations Manager 2012? (To answer, select the appropriate action for each server
in the answer area.)

What should you configure?

###BeginCaseStudy###
Case Study: 1
Trey research
Scenario
Trey Research is a consulting company.
Trey Research has three offices. The offices are located in Seattle, Los Angeles, and Toronto.
Trey Research has two data centers. The data centers are located in Los Angeles and Toronto.
Existing Environment
The network contains a single-domain Active Directory forest named treyresearch.com. The network
contains switches that support either SNMPv1 or SNMPv2.
The forest contains 100 physical servers that run Windows Server 2008 R2 Service Pack 1 (SP1).
The relevant servers are configured as shown in the following table.

All of the System Center 2012 servers use Servers as a database server.
All of the VMM components in the production environment are installed on Server1. Server1 is
located in the Los Angeles data center.
Ten virtual machine hosts are located in the Toronto data center and 90 virtual machine hosts are
located in the Los Angeles data center.
Server9 is used to manage three virtualization hosts in a lab environment.
Requirements
Planned Changes
Trey Research plans to implement the following changes:
• Upgrade Servers to VMM 2012.
• Discover and monitor network switches by using Operations Manager.
• Grant the network technicians the required permissions to configure the network fabric.
• Install a System Center 2012 Service Manager management server on Server7 and a Service
Manager data warehouse management server on Servers.
• Provide external access to the Virtual Machine Manager Self-Service Portal (VMMSSP) by
using the names ssp.treyresearch.com and vmm.treyresearch.com.
Private Cloud Infrastructure Requirements
Trey Research identifies the following requirements for the private cloud infrastructure:
• Integrate VMM 2012 and Operations Manager 2012.
• Ensure that all VMM 2012 components are highly available.
• Ensure that virtual machines use a MAC address from a custom MAC address pool.
• Ensure that Hyper-V hosts can be deployed to bare-metal computers from Server6.
• Control the placement of virtual machines based on the performance data gathered by
Operations Manager.
Private Cloud Compliance Requirements
Trey Research identifies the following requirements for compliance in the private cloud
infrastructure:
• Ensure that updates on the Hyper-V hosts can be remediated.
• Generate the compliance status of all the servers in the fabric.
• Ensure that update baselines for all of the servers in the fabric are created.
Private Cloud Services Requirements
Trey Research identifies the following requirements for managing services in the private cloud:
• Users in the human resources department must be able to create virtual machines that have
two CPUs and 4 GB RAM by using the VMMSSP.

• Users in the marketing department must be able to create new virtual machines that will be
hosted in the Toronto office. The virtual machine templates for the marketing department users
must be stored in the Toronto office.

###EndCaseStudy###

You need to configure VMM 2012 to meet the private cloud services requirements for the human
resources department users. What should you configure? (Each correct answer presents part of the
solution. Choose all that apply.)

What should you include in the recommendation?

###BeginCaseStudy###
Case Study: 1
Trey research
Scenario
Trey Research is a consulting company.
Trey Research has three offices. The offices are located in Seattle, Los Angeles, and Toronto.
Trey Research has two data centers. The data centers are located in Los Angeles and Toronto.
Existing Environment
The network contains a single-domain Active Directory forest named treyresearch.com. The network
contains switches that support either SNMPv1 or SNMPv2.
The forest contains 100 physical servers that run Windows Server 2008 R2 Service Pack 1 (SP1).
The relevant servers are configured as shown in the following table.

All of the System Center 2012 servers use Servers as a database server.
All of the VMM components in the production environment are installed on Server1. Server1 is
located in the Los Angeles data center.
Ten virtual machine hosts are located in the Toronto data center and 90 virtual machine hosts are
located in the Los Angeles data center.
Server9 is used to manage three virtualization hosts in a lab environment.
Requirements
Planned Changes
Trey Research plans to implement the following changes:
• Upgrade Servers to VMM 2012.
• Discover and monitor network switches by using Operations Manager.
• Grant the network technicians the required permissions to configure the network fabric.
• Install a System Center 2012 Service Manager management server on Server7 and a Service
Manager data warehouse management server on Servers.
• Provide external access to the Virtual Machine Manager Self-Service Portal (VMMSSP) by
using the names ssp.treyresearch.com and vmm.treyresearch.com.
Private Cloud Infrastructure Requirements
Trey Research identifies the following requirements for the private cloud infrastructure:
• Integrate VMM 2012 and Operations Manager 2012.
• Ensure that all VMM 2012 components are highly available.
• Ensure that virtual machines use a MAC address from a custom MAC address pool.
• Ensure that Hyper-V hosts can be deployed to bare-metal computers from Server6.
• Control the placement of virtual machines based on the performance data gathered by
Operations Manager.
Private Cloud Compliance Requirements
Trey Research identifies the following requirements for compliance in the private cloud
infrastructure:
• Ensure that updates on the Hyper-V hosts can be remediated.
• Generate the compliance status of all the servers in the fabric.
• Ensure that update baselines for all of the servers in the fabric are created.
Private Cloud Services Requirements
Trey Research identifies the following requirements for managing services in the private cloud:
• Users in the human resources department must be able to create virtual machines that have
two CPUs and 4 GB RAM by using the VMMSSP.

• Users in the marketing department must be able to create new virtual machines that will be
hosted in the Toronto office. The virtual machine templates for the marketing department users
must be stored in the Toronto office.

###EndCaseStudy###

You need to recommend changes to Server9 before you upgrade to VMM 2012. What should you
include in the recommendation?

Which Run As Account type should you use?

###BeginCaseStudy###
Case Study: 1
Trey research
Scenario
Trey Research is a consulting company.
Trey Research has three offices. The offices are located in Seattle, Los Angeles, and Toronto.
Trey Research has two data centers. The data centers are located in Los Angeles and Toronto.
Existing Environment
The network contains a single-domain Active Directory forest named treyresearch.com. The network
contains switches that support either SNMPv1 or SNMPv2.
The forest contains 100 physical servers that run Windows Server 2008 R2 Service Pack 1 (SP1).
The relevant servers are configured as shown in the following table.

All of the System Center 2012 servers use Servers as a database server.
All of the VMM components in the production environment are installed on Server1. Server1 is
located in the Los Angeles data center.
Ten virtual machine hosts are located in the Toronto data center and 90 virtual machine hosts are
located in the Los Angeles data center.
Server9 is used to manage three virtualization hosts in a lab environment.
Requirements
Planned Changes
Trey Research plans to implement the following changes:
• Upgrade Servers to VMM 2012.
• Discover and monitor network switches by using Operations Manager.
• Grant the network technicians the required permissions to configure the network fabric.
• Install a System Center 2012 Service Manager management server on Server7 and a Service
Manager data warehouse management server on Servers.
• Provide external access to the Virtual Machine Manager Self-Service Portal (VMMSSP) by
using the names ssp.treyresearch.com and vmm.treyresearch.com.
Private Cloud Infrastructure Requirements
Trey Research identifies the following requirements for the private cloud infrastructure:
• Integrate VMM 2012 and Operations Manager 2012.
• Ensure that all VMM 2012 components are highly available.
• Ensure that virtual machines use a MAC address from a custom MAC address pool.
• Ensure that Hyper-V hosts can be deployed to bare-metal computers from Server6.
• Control the placement of virtual machines based on the performance data gathered by
Operations Manager.
Private Cloud Compliance Requirements
Trey Research identifies the following requirements for compliance in the private cloud
infrastructure:
• Ensure that updates on the Hyper-V hosts can be remediated.
• Generate the compliance status of all the servers in the fabric.
• Ensure that update baselines for all of the servers in the fabric are created.
Private Cloud Services Requirements
Trey Research identifies the following requirements for managing services in the private cloud:
• Users in the human resources department must be able to create virtual machines that have
two CPUs and 4 GB RAM by using the VMMSSP.

• Users in the marketing department must be able to create new virtual machines that will be
hosted in the Toronto office. The virtual machine templates for the marketing department users
must be stored in the Toronto office.

###EndCaseStudy###

HOTSPOT
You need to implement the planned changes for Operations Manager. Which Run As Account type
should you use? (To answer, select the appropriate Run As Account for each switch type in the
answer area.)

which node should you perform the configuration?

###BeginCaseStudy###
Case Study: 2
Contoso Ltd
Scenario
Contoso, Ltd. is a manufacturing company.
Contoso has a main office and six branch offices. The main office is located in Toronto. The branch
offices are located in New York, Seattle, Miami, Montreal, Los Angeles, and Vancouver.
Existing Environment
Active Directory Environment
The network contains an Active Directory forest named contoso.com. The forest contains a child
domain for each office.
Active Directory currently contains 7,500 user accounts and 15,000 computer accounts.
Network Infrastructure
All servers are located in a data center in Toronto. The data center contains multiple subnets that
are separated by firewalls.
The Toronto data center contains a cluster that runs Microsoft SQL Server 2008 Enterprise Service
Pack 1 (SP1).
Four servers are unused and are being considered as potential Hyper-V hosts. The servers are
configured as shown in the following table.

All of the servers being considered as potential Hyper-V hosts have both locally attached storage and
access to a SAN.

Help Desk Environment
Contoso uses a help desk ticketing system that was developed in-house. Fifty help desk agents have
access to the ticketing system. The ticketing system currently tracks:
• An average of two new incidents per month, per client computer
• An average of 2,000 change requests per month
Disaster Recovery Environment
Contoso uses a third-party backup solution. Backups are scheduled for the servers in the
Seattle office as follows:
• The daily incremental backups total 10 GB.
• The total size of data to back up is 100 GB.
• Backed up data is retained for 10 business days.
Problem Statements
The original developers of the help desk ticketing system are no longer employed by Contoso and
maintenance of the system is becoming an issue.
Requirements
Planned Changes
Contoso plans to move the IT infrastructure to a private cloud. Whenever possible, hardware and
software costs must be minimized.
Contoso plans to open a small office in Beijing. System Center 2012 App Controller will be used to
manage applications. The display names of the applications will be in Simplified Chinese Pinyin IME.
New physical servers will be deployed by using System Center 2012 Configuration
Manager from a server named Servers. Servers will also be a PXE service point.
The current backup solution will be replaced with System Center 2012 Data Protection Manager
(DPM).
A public key infrastructure (PKI) will be deployed to issue and manage certificates. The PKI
deployment must be made as secure as possible.
Hardware load balancers will be deployed for use in the deployment of private cloud services.
Cloud Requirements
Contoso plans to implement a cloud solution that meets the following requirements:
• Stores all virtual machines on the SAN only.
• Uses SAN copy to provision the virtual machines.
• Provides the ability to manage the resolution of incidents.
• Contains managed virtual machines across both private and public clouds.
• Provides the ability to customize the settings of management packs provided by Microsoft.
• Collects security events from all of the servers running in the private cloud and provides
centralized reporting on the events.
App1 Requirements
A new application named App1 will be deployed to the private cloud. App1 is a three-tier application
that contains the following components:
• A front-end tier that runs a web server. The tier must be highly available and capable of
being quickly scaled out if required.
• A middle tier that runs an application server.
• A back-end tier that runs a database.
App2 Requirements
An application named App2 will be deployed to the public cloud. Users will be authenticated by
using the on-premises Active Directory. The users must be able to access App2 without being
prompted for authentication again.

###EndCaseStudy###

HOTSPOT
You need to configure the Hyper-V hosts to meet the cloud requirements. From which node should
you perform the configuration? (To answer, select the appropriate node in the answer area.)

Which components should you identify?

###BeginCaseStudy###
Case Study: 2
Contoso Ltd
Scenario
Contoso, Ltd. is a manufacturing company.
Contoso has a main office and six branch offices. The main office is located in Toronto. The branch
offices are located in New York, Seattle, Miami, Montreal, Los Angeles, and Vancouver.
Existing Environment
Active Directory Environment
The network contains an Active Directory forest named contoso.com. The forest contains a child
domain for each office.
Active Directory currently contains 7,500 user accounts and 15,000 computer accounts.
Network Infrastructure
All servers are located in a data center in Toronto. The data center contains multiple subnets that
are separated by firewalls.
The Toronto data center contains a cluster that runs Microsoft SQL Server 2008 Enterprise Service
Pack 1 (SP1).
Four servers are unused and are being considered as potential Hyper-V hosts. The servers are
configured as shown in the following table.

All of the servers being considered as potential Hyper-V hosts have both locally attached storage and
access to a SAN.

Help Desk Environment
Contoso uses a help desk ticketing system that was developed in-house. Fifty help desk agents have
access to the ticketing system. The ticketing system currently tracks:
• An average of two new incidents per month, per client computer
• An average of 2,000 change requests per month
Disaster Recovery Environment
Contoso uses a third-party backup solution. Backups are scheduled for the servers in the
Seattle office as follows:
• The daily incremental backups total 10 GB.
• The total size of data to back up is 100 GB.
• Backed up data is retained for 10 business days.
Problem Statements
The original developers of the help desk ticketing system are no longer employed by Contoso and
maintenance of the system is becoming an issue.
Requirements
Planned Changes
Contoso plans to move the IT infrastructure to a private cloud. Whenever possible, hardware and
software costs must be minimized.
Contoso plans to open a small office in Beijing. System Center 2012 App Controller will be used to
manage applications. The display names of the applications will be in Simplified Chinese Pinyin IME.
New physical servers will be deployed by using System Center 2012 Configuration
Manager from a server named Servers. Servers will also be a PXE service point.
The current backup solution will be replaced with System Center 2012 Data Protection Manager
(DPM).
A public key infrastructure (PKI) will be deployed to issue and manage certificates. The PKI
deployment must be made as secure as possible.
Hardware load balancers will be deployed for use in the deployment of private cloud services.
Cloud Requirements
Contoso plans to implement a cloud solution that meets the following requirements:
• Stores all virtual machines on the SAN only.
• Uses SAN copy to provision the virtual machines.
• Provides the ability to manage the resolution of incidents.
• Contains managed virtual machines across both private and public clouds.
• Provides the ability to customize the settings of management packs provided by Microsoft.
• Collects security events from all of the servers running in the private cloud and provides
centralized reporting on the events.
App1 Requirements
A new application named App1 will be deployed to the private cloud. App1 is a three-tier application
that contains the following components:
• A front-end tier that runs a web server. The tier must be highly available and capable of
being quickly scaled out if required.
• A middle tier that runs an application server.
• A back-end tier that runs a database.
App2 Requirements
An application named App2 will be deployed to the public cloud. Users will be authenticated by
using the on-premises Active Directory. The users must be able to access App2 without being
prompted for authentication again.

###EndCaseStudy###

DRAG DROP
You need to identify which System Center 2012 components are required to meet the cloud
requirements. Which components should you identify? (To answer, drag the appropriate
components to the correct requirements. Each component may be used once, more than once, or
not at all. You may need to drag the split bar between panes or scroll to view content.)

What should you identify?

###BeginCaseStudy###
Case Study: 2
Contoso Ltd
Scenario
Contoso, Ltd. is a manufacturing company.
Contoso has a main office and six branch offices. The main office is located in Toronto. The branch
offices are located in New York, Seattle, Miami, Montreal, Los Angeles, and Vancouver.
Existing Environment
Active Directory Environment
The network contains an Active Directory forest named contoso.com. The forest contains a child
domain for each office.
Active Directory currently contains 7,500 user accounts and 15,000 computer accounts.
Network Infrastructure
All servers are located in a data center in Toronto. The data center contains multiple subnets that
are separated by firewalls.
The Toronto data center contains a cluster that runs Microsoft SQL Server 2008 Enterprise Service
Pack 1 (SP1).
Four servers are unused and are being considered as potential Hyper-V hosts. The servers are
configured as shown in the following table.

All of the servers being considered as potential Hyper-V hosts have both locally attached storage and
access to a SAN.

Help Desk Environment
Contoso uses a help desk ticketing system that was developed in-house. Fifty help desk agents have
access to the ticketing system. The ticketing system currently tracks:
• An average of two new incidents per month, per client computer
• An average of 2,000 change requests per month
Disaster Recovery Environment
Contoso uses a third-party backup solution. Backups are scheduled for the servers in the
Seattle office as follows:
• The daily incremental backups total 10 GB.
• The total size of data to back up is 100 GB.
• Backed up data is retained for 10 business days.
Problem Statements
The original developers of the help desk ticketing system are no longer employed by Contoso and
maintenance of the system is becoming an issue.
Requirements
Planned Changes
Contoso plans to move the IT infrastructure to a private cloud. Whenever possible, hardware and
software costs must be minimized.
Contoso plans to open a small office in Beijing. System Center 2012 App Controller will be used to
manage applications. The display names of the applications will be in Simplified Chinese Pinyin IME.
New physical servers will be deployed by using System Center 2012 Configuration
Manager from a server named Servers. Servers will also be a PXE service point.
The current backup solution will be replaced with System Center 2012 Data Protection Manager
(DPM).
A public key infrastructure (PKI) will be deployed to issue and manage certificates. The PKI
deployment must be made as secure as possible.
Hardware load balancers will be deployed for use in the deployment of private cloud services.
Cloud Requirements
Contoso plans to implement a cloud solution that meets the following requirements:
• Stores all virtual machines on the SAN only.
• Uses SAN copy to provision the virtual machines.
• Provides the ability to manage the resolution of incidents.
• Contains managed virtual machines across both private and public clouds.
• Provides the ability to customize the settings of management packs provided by Microsoft.
• Collects security events from all of the servers running in the private cloud and provides
centralized reporting on the events.
App1 Requirements
A new application named App1 will be deployed to the private cloud. App1 is a three-tier application
that contains the following components:
• A front-end tier that runs a web server. The tier must be highly available and capable of
being quickly scaled out if required.
• A middle tier that runs an application server.
• A back-end tier that runs a database.
App2 Requirements
An application named App2 will be deployed to the public cloud. Users will be authenticated by
using the on-premises Active Directory. The users must be able to access App2 without being
prompted for authentication again.

###EndCaseStudy###

You need to identify what you require from the vendor of the hardware load balancer to support the
planned changes. What should you identify?

Which three actions should you perform in sequence?

###BeginCaseStudy###
Case Study: 2
Contoso Ltd
Scenario
Contoso, Ltd. is a manufacturing company.
Contoso has a main office and six branch offices. The main office is located in Toronto. The branch
offices are located in New York, Seattle, Miami, Montreal, Los Angeles, and Vancouver.
Existing Environment
Active Directory Environment
The network contains an Active Directory forest named contoso.com. The forest contains a child
domain for each office.
Active Directory currently contains 7,500 user accounts and 15,000 computer accounts.
Network Infrastructure
All servers are located in a data center in Toronto. The data center contains multiple subnets that
are separated by firewalls.
The Toronto data center contains a cluster that runs Microsoft SQL Server 2008 Enterprise Service
Pack 1 (SP1).
Four servers are unused and are being considered as potential Hyper-V hosts. The servers are
configured as shown in the following table.

All of the servers being considered as potential Hyper-V hosts have both locally attached storage and
access to a SAN.

Help Desk Environment
Contoso uses a help desk ticketing system that was developed in-house. Fifty help desk agents have
access to the ticketing system. The ticketing system currently tracks:
• An average of two new incidents per month, per client computer
• An average of 2,000 change requests per month
Disaster Recovery Environment
Contoso uses a third-party backup solution. Backups are scheduled for the servers in the
Seattle office as follows:
• The daily incremental backups total 10 GB.
• The total size of data to back up is 100 GB.
• Backed up data is retained for 10 business days.
Problem Statements
The original developers of the help desk ticketing system are no longer employed by Contoso and
maintenance of the system is becoming an issue.
Requirements
Planned Changes
Contoso plans to move the IT infrastructure to a private cloud. Whenever possible, hardware and
software costs must be minimized.
Contoso plans to open a small office in Beijing. System Center 2012 App Controller will be used to
manage applications. The display names of the applications will be in Simplified Chinese Pinyin IME.
New physical servers will be deployed by using System Center 2012 Configuration
Manager from a server named Servers. Servers will also be a PXE service point.
The current backup solution will be replaced with System Center 2012 Data Protection Manager
(DPM).
A public key infrastructure (PKI) will be deployed to issue and manage certificates. The PKI
deployment must be made as secure as possible.
Hardware load balancers will be deployed for use in the deployment of private cloud services.
Cloud Requirements
Contoso plans to implement a cloud solution that meets the following requirements:
• Stores all virtual machines on the SAN only.
• Uses SAN copy to provision the virtual machines.
• Provides the ability to manage the resolution of incidents.
• Contains managed virtual machines across both private and public clouds.
• Provides the ability to customize the settings of management packs provided by Microsoft.
• Collects security events from all of the servers running in the private cloud and provides
centralized reporting on the events.
App1 Requirements
A new application named App1 will be deployed to the private cloud. App1 is a three-tier application
that contains the following components:
• A front-end tier that runs a web server. The tier must be highly available and capable of
being quickly scaled out if required.
• A middle tier that runs an application server.
• A back-end tier that runs a database.
App2 Requirements
An application named App2 will be deployed to the public cloud. Users will be authenticated by
using the on-premises Active Directory. The users must be able to access App2 without being
prompted for authentication again.

###EndCaseStudy###

DRAG DROP
You need to configure the storage fabric to support the deployment of the virtual machines. The
solution must meet the cloud requirements. Which three actions should you perform in sequence?
(To answer, move the appropriate three actions from the list of actions to the answer area and
arrange them in the correct order.)

Which port or ports should you identify?

###BeginCaseStudy###
Case Study: 2
Contoso Ltd
Scenario
Contoso, Ltd. is a manufacturing company.
Contoso has a main office and six branch offices. The main office is located in Toronto. The branch
offices are located in New York, Seattle, Miami, Montreal, Los Angeles, and Vancouver.
Existing Environment
Active Directory Environment
The network contains an Active Directory forest named contoso.com. The forest contains a child
domain for each office.
Active Directory currently contains 7,500 user accounts and 15,000 computer accounts.
Network Infrastructure
All servers are located in a data center in Toronto. The data center contains multiple subnets that
are separated by firewalls.
The Toronto data center contains a cluster that runs Microsoft SQL Server 2008 Enterprise Service
Pack 1 (SP1).
Four servers are unused and are being considered as potential Hyper-V hosts. The servers are
configured as shown in the following table.

All of the servers being considered as potential Hyper-V hosts have both locally attached storage and
access to a SAN.

Help Desk Environment
Contoso uses a help desk ticketing system that was developed in-house. Fifty help desk agents have
access to the ticketing system. The ticketing system currently tracks:
• An average of two new incidents per month, per client computer
• An average of 2,000 change requests per month
Disaster Recovery Environment
Contoso uses a third-party backup solution. Backups are scheduled for the servers in the
Seattle office as follows:
• The daily incremental backups total 10 GB.
• The total size of data to back up is 100 GB.
• Backed up data is retained for 10 business days.
Problem Statements
The original developers of the help desk ticketing system are no longer employed by Contoso and
maintenance of the system is becoming an issue.
Requirements
Planned Changes
Contoso plans to move the IT infrastructure to a private cloud. Whenever possible, hardware and
software costs must be minimized.
Contoso plans to open a small office in Beijing. System Center 2012 App Controller will be used to
manage applications. The display names of the applications will be in Simplified Chinese Pinyin IME.
New physical servers will be deployed by using System Center 2012 Configuration
Manager from a server named Servers. Servers will also be a PXE service point.
The current backup solution will be replaced with System Center 2012 Data Protection Manager
(DPM).
A public key infrastructure (PKI) will be deployed to issue and manage certificates. The PKI
deployment must be made as secure as possible.
Hardware load balancers will be deployed for use in the deployment of private cloud services.
Cloud Requirements
Contoso plans to implement a cloud solution that meets the following requirements:
• Stores all virtual machines on the SAN only.
• Uses SAN copy to provision the virtual machines.
• Provides the ability to manage the resolution of incidents.
• Contains managed virtual machines across both private and public clouds.
• Provides the ability to customize the settings of management packs provided by Microsoft.
• Collects security events from all of the servers running in the private cloud and provides
centralized reporting on the events.
App1 Requirements
A new application named App1 will be deployed to the private cloud. App1 is a three-tier application
that contains the following components:
• A front-end tier that runs a web server. The tier must be highly available and capable of
being quickly scaled out if required.
• A middle tier that runs an application server.
• A back-end tier that runs a database.
App2 Requirements
An application named App2 will be deployed to the public cloud. Users will be authenticated by
using the on-premises Active Directory. The users must be able to access App2 without being
prompted for authentication again.

###EndCaseStudy###

You need to identify which UDP port or ports must be opened on any of the firewalls between
Server5 and all of the subnets in the data center. The solution must minimize the number of ports
opened on the firewall. Which port or ports should you identify? (Each correct answer presents part
of the solution. Choose all that apply.)