You need to ensure that your timesheet matches the task updates
In a project that is published to Microsoft Office Project Server 2007, you have entered time against your tasks in your timesheet, but that time is not recorded in your task updates. You need to ensure that your timesheet matches the task updates. What should you do?
You need to find out how many and which deliverables are due each day for the next 2 months
Several projects that are published to Microsoft Office Project Server 2007 have many linked deliverables. You need to find out how many and which deliverables are due each day for the next 2 months. What should you do?
You need to get a status report from your team
You are checking on the status of a project that is published to Microsoft Office Project Server 2007. You want more recent information than is available in the latest status report, but you dont want to wait for the next regularly scheduled status report. You need to get a status report from your team. What should you do?
you need to track this risk for the new tasks
You manage a large-scale project that is saved to Microsoft Office Project Server 2007. Several tasks already have a risk associated with them. You are adding additional tasks that will also have this associated risk. In Microsoft Office Project Web Access, you need to track this risk for the new tasks. What should you do?
you need to display the cost-to-date for each resource on this project
You create a project and save it to Microsoft Office Project Server 2007.
Working in Microsoft Office Project Web Access, you need to display the cost-to-date for each resource on this project. What should you do?
you need to track this risk for the new tasks
You manage a large-scale project that is saved to Microsoft Office Project Server 2007. Several tasks already have a risk associated with them. You are adding additional tasks that will also have this associated risk. In Microsoft Office Project Web Access, you need to track this risk for the new tasks. What should you do?
you need to propose these resource assignments so that senior management can review and approve them
You are developing a project that is published to Microsoft Office Project Server 2007. You have identified the resources you want to work on your project. In Microsoft Office Project Web Access, you need to propose these resource assignments so that senior management can review and approve them. What should you do?
You need to modify the activity plan to accommodate the additional tasks and allow resources to continue to tr
You are managing an activity plan in Microsoft Office Project Server 2007.
You identify additional tasks with complex dependencies and multiple resources per task. You need to modify the activity plan to accommodate the additional tasks and allow resources to continue to track their work by using timesheets. What should you do?
You need to check resource availability to ascertain how much free time the resources required for the new pro
You manage a portfolio of projects that are saved to Microsoft Office Project Server 2007. Your organization is evaluating whether to take on another project. A key factor in that decision is whether the necessary resources will be available during the next 3 months. Your organization’s resources include full-time and part-time regular employees and some contractors with variable schedules. You need to check resource availability to ascertain how much free time the resources required for the new project will have during the next 3 months. What should you do?
Where can you view availability of resources while you assign them to the project plan?
You assign resources to a project plan in Microsoft Office Project Professional 2007. Several times a day, other project managers are doing the same. You need to ensure that the resources are available before you assign them. Where can you view availability of resources while you assign them to the project plan?