Exam 70-633: TS: Microsoft Office Project Server 2007, Managing Projects

You need to find a temporary solution so that the resource’s timesheet can be submitted on time

A resource assigned to a project that is published to Microsoft Office Project Server 2007 cannot access Project Server. Timesheets are due this afternoon, and the resource needs to indicate that she worked 6 hours instead of the planned 8. You need to find a temporary solution so that the resource’s timesheet can be submitted on time. What should you do?

What should you create for each property?

You manage different kinds of documents. Each document has different properties, such as phase, category, and team. Documents in one phase may relate to multiple categories and teams. You do not want to upload documents more than once. You need to organize the documents so that you can filter for documents by phase, category, or team on one page. What should you create for each property?

You need to submit all your outstanding task updates

In Microsoft Office Project Web Access, you report time spent on project tasks in your weekly timesheets. You have not submitted your timesheets for over a month, but you have kept them up to date and saved them. Your project manager says she has received no task updates from you since the project started 3 weeks ago. You need to submit all your outstanding task updates. What should you do first?

You need to link Task A and Task B so that they occur in sequence, with the start date for Task B 5 days after

You are working in Microsoft Office Project Professional 2007 on a project plan in which Task A and Task B are independent. However, Task B must start 5 days after Task A is completed. You need to link Task A and Task B so that they occur in sequence, with the start date for Task B 5 days after the finish date for Task A. What should you do?