Exam 70-633: TS: Microsoft Office Project Server 2007, Managing Projects

You need to track the cost of this resource to the project as he completes work and submits his timesheets

You manage a project that is saved to Microsoft Office Project Server 2007.
One of the resources working on the project is an external contractor. His cost to the project is a fixed price per hour of work performed. To add this resource to the enterprise resource pool, you fill out a new resource form on the Resource Center page in Microsoft Office Project Web Access. You need to track the cost of this resource to the project as he completes work and submits his timesheets. What should you do?

You need to generate a report now that contains the latest information

Resources have submitted time worked for a project that is published to Microsoft Office Project Server 2007, and you have accepted their updates into the plan. However, when you view a report on the Data Analysis page of Microsoft Office Project Web Access, you notice that the updates are not in the report. You need to generate a report now that contains the latest information.
What should you do?