You need to submit the schedule tomorrow with this task allocated to two resources

The project you are creating in Microsoft Office Project Standard 2007 includes a task with definite deadlines. Completing the task work by the deadline requires two resources with specific skills. Only one resource with these skills is available. You need to submit the schedule tomorrow with this task allocated to two resources. What should you do?

You need to set up the task to correctly represent the available information

You are managing a project schedule in Microsoft Office Project Standard 2007. A task assigned to a resource will take 10 hours to complete. Due to other project commitments, he requires 3 weeks to complete the task and will not finish early. The project schedule is based on a Monday-to-Friday work week and an 8-hour work day. You need to set up the task to correctly represent the available information. What should you do first?

You need to modify the schedule to meet the original finish date

You are managing a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: Task 1 is 100 percent complete. Tasks 2 and 4 are each 50 percent complete. The forecast duration of Task 2 is half a week more than its baseline duration. Task 3 cannot start until Task 2 is complete. Task 4 is 1 week late. You need to modify the schedule to meet the original finish date. What should you do?