You need to submit the schedule tomorrow with this task allocated to two resources
The project you are creating in Microsoft Office Project Standard 2007 includes a task with definite deadlines. Completing the task work by the deadline requires two resources with specific skills. Only one resource with these skills is available. You need to submit the schedule tomorrow with this task allocated to two resources. What should you do?
You need to forecast when the project will need resources with specific skills
You are creating a schedule in Microsoft Office Project Professional 2007. For budgeting purposes, you allocate resources 6 months in advance of the project. You do not know who will be assigned to your project at this time. You need to forecast when the project will need resources with specific skills. What should you do?
You need to track project expenditures for each task on the project schedule
You are managing a project schedule in Microsoft Office Project Standard 2007. You have several team members who will be spending money on tasks they are assigned to. You need to track project expenditures for each task on the project schedule. What should you do?
you need to ensure that high importance tasks are not affected by this action
You create a project plan in Microsoft Office Project Standard 2007 and assign resources to tasks. Some tasks are of high importance. You must not over-allocate resources in the project plan. Before leveling the schedule, you need to ensure that high importance tasks are not affected by this action.
What should you do?
You need to set up the task to correctly represent the available information
You are managing a project schedule in Microsoft Office Project Standard 2007. A task assigned to a resource will take 10 hours to complete. Due to other project commitments, he requires 3 weeks to complete the task and will not finish early. The project schedule is based on a Monday-to-Friday work week and an 8-hour work day. You need to set up the task to correctly represent the available information. What should you do first?
Which tasks are on the critical path?
In Microsoft Office Project Standard 2007, you create the following project plan: You need to identify the critical path. Which tasks are on the critical path?
What should you include in a usage view?
Your project has a fixed resource budget. In Microsoft Office Project Standard 2007, you assign the budget to the project plan, and you assign resources with a standard rate to the project tasks. Then you display the project summary task. You need to compare the budget cost with the project cost.
What should you include in a usage view?
You need to modify the schedule to meet the original finish date
You are managing a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: Task 1 is 100 percent complete. Tasks 2 and 4 are each 50 percent complete. The forecast duration of Task 2 is half a week more than its baseline duration. Task 3 cannot start until Task 2 is complete. Task 4 is 1 week late. You need to modify the schedule to meet the original finish date. What should you do?
You need to immediately display the effect of your changes on the start and finish dates of other tasks
In Microsoft Office Project Standard 2007, you are changing the durations of several tasks in a project schedule. You need to immediately display the effect of your changes on the start and finish dates of other tasks. What should you do?
You need to set up the schedule so you can easily switch between viewing all tasks organized by WBS and by the
You are preparing a multi-year project schedule in Microsoft Office Project Standard 2007. You need to set up the schedule so you can easily switch between viewing all tasks organized by WBS and by the month they are scheduled to end. What should you do?