PrepAway - Latest Free Exam Questions & Answers

Category: 70-632

Exam 70-632: TS: Microsoft Office Project 2007, Managing Projects

What are two possible ways to achieve this goal? (Each correct answer presents a complete solution

You are managing a project schedule in Microsoft Office Project Standard 2007. You create 100 new tasks in the project plan. Each task has a duration of 5 days, which you indicate by entering 5 in the Duration field. After every third task you create, Project displays a message about an alternative method of setting the task duration. You need to stop the message from appearing. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

You need to ascertain whether the resource is overallocated during the first month of the schedule

You are developing a project schedule in Microsoft Office Project Standard 2007. The project uses a shared resource pool. One of the resources assigned to the project is assigned to another project on a half-time basis during the first month of the project. You need to ascertain whether the resource is overallocated during the first month of the schedule. What should you do first?

you need to resolve as many of the situations creating red-indicated resources as possible

You are managing a project plan in Microsoft Office Project Standard 2007. Midway through the project, some resource names appear in red in the Resource Usage view. You find that many of these resources have no remaining availability for specific days but are completely available on subsequent days. Your organization has a strict policy that resources can work no more than a total of 115 percent in each period of 20 work days. However, the organization wants resources to be utilized as much as possible. When you level your schedule, you need to resolve as many of the situations creating red-indicated resources as possible. What should you do?

You need to increase the task duration to 4 days, and ensure that the effort associated with the task does not

You are managing a project schedule in Microsoft Office Project Standard 2007. You create a fixed units task with a duration of 2 days. You have not yet assigned resources to the task. You need to increase the task duration to 4 days, and ensure that the effort associated with the task does not change. What should you do?

What task type should you use?

You are managing a project schedule in Microsoft Office Project Standard 2007. You originally thought one resource could complete a task in 10 days. You now think it will take the full-time effort of two resources to complete the task by the original finish date. You need to ensure that when you add the second resource, Project maintains the original finish date. What task type should you use?


Page 8 of 17« First...678910...Last »