You need to calculate the number of resources necessary to complete the task in the required time
You are creating a project plan in Microsoft Office Project Standard 2007. A task in your plan has a fixed duration of 10 days. You have an estimate of how many hours of work the task will require. You need to calculate the number of resources necessary to complete the task in the required time.
What should you do?
Which dependency should you create?
You take responsibility for tracking an existing schedule in Microsoft Office Project Standard 2007. The project schedule uses the default Standard calendar. There are no constraints on your project. You need to order computer equipment for your development environment. Your supplier will deliver the equipment three weeks after receiving a purchase order. You enter a milestone for the purchase order date and create an equipment installation task. You need to create a dependency from the purchase order task to the equipment installation task so you can schedule the equipment installation based on a specific purchase order date. Which dependency should you create?
You need to estimate the total cost of the project
You are building a project plan in Microsoft Office Project Standard 2007. You expand the project plan to display all outline levels and the project summary task. You enter resources and their costs. You have not yet set a baseline. You need to estimate the total cost of the project. What should you do?
You need to create a summary task from an Outline Level 1 task
In Microsoft Office Project Standard 2007, you are viewing a project plan in the default Gantt Chart view. You need to create a summary task from an Outline Level 1 task. What should you do?
You need to predict the effect of changing the duration of Task 2 to two weeks
You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: You need to predict the effect of changing the duration of Task 2 to two weeks. What is the result?
You need to decrease the project duration
You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: All tasks are set to fixed work. Only the resources shown in the above project plan are assigned to the tasks. Both resources have the same skill set. You need to decrease the project duration. What should you do?
You need to ascertain the late finish of Task 4
You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: You need to ascertain the late finish of Task 4. What is the result?
Which dependency should you delete?
You are editing a schedule in Microsoft Office Project Standard 2007, scheduling from the start of the project. You notice that Task X is starting later than you expected. Task W is 100 percent complete. You need Task X to start on Tuesday. Which dependency should you delete?
You need to represent the relationship from Task B to Task A in the project schedules
You are managing two project schedules in Microsoft Office Project Standard 2007. Task A in Project Alpha cannot begin until Task B in Project Bravo is complete. You insert both projects into a master project. You need to represent the relationship from Task B to Task A in the project schedules. What should you do?
You need to select the appropriate view in which to update your project with resource hours worked per week
You are tracking a project in Microsoft Office Project Standard 2007. You need to select the appropriate view in which to update your project with resource hours worked per week. What should you do?