PrepAway - Latest Free Exam Questions & Answers

Category: 70-632

Exam 70-632: TS: Microsoft Office Project 2007, Managing Projects

What should you do?

You are creating a project schedule in Microsoft Office Project Standard 2007. You set the project start date to today and enter a task. You notice that the year shown in the project timescale does not match the date shown in the date field. You need the timescale to show the current year instead of the next year. What should you do?

What should you do?

You are entering tasks in a project you are tracking in Microsoft Office Project Standard 2007. You enter the duration of each task. Then you assign multiple resources to each task. As a result, the duration of the tasks changes. You want the duration of all future tasks to automatically remain the same when you assign resources to those tasks. What should you do?

What should you do?

You are entering tasks in a project you are tracking in Microsoft Office Project Standard 2007. You enter the duration of each task. Then you assign multiple resources to each task. As a result, the duration of the tasks changes. You want the duration of all future tasks to automatically remain the same when you assign resources to those tasks. What should you do?

You need to update the schedule to reflect the new Resource B work estimate

You are tracking a project in Microsoft Office Project Standard 2007. Resources A and B are each assigned to work 40 hours on a task. After each resource works 30 hours, you update the schedule to reflect the actual work to date. Resource B estimates that she will need to work a total of 50 hours to complete her task assignment. You need to update the schedule to reflect the new Resource B work estimate. What should you do?

you need to ensure that your project costs reflect the new hourly rate

You use Microsoft Office Project Standard 2007 to track your project schedule. You assign a resource to tasks scheduled during normal working hours. Starting the first of next month, the hourly rate of this resource will increase by 20 percent. Without changing any of the resource’s assignments, you need to ensure that your project costs reflect the new hourly rate. What should you do?


Page 4 of 17« First...23456...10...Last »