What should you do?
You are creating a project schedule in Microsoft Office Project Standard 2007. You set the project start date to today and enter a task. You notice that the year shown in the project timescale does not match the date shown in the date field. You need the timescale to show the current year instead of the next year. What should you do?
What should you do?
You are entering tasks in a project you are tracking in Microsoft Office Project Standard 2007. You enter the duration of each task. Then you assign multiple resources to each task. As a result, the duration of the tasks changes. You want the duration of all future tasks to automatically remain the same when you assign resources to those tasks. What should you do?
What should you do?
You are entering tasks in a project you are tracking in Microsoft Office Project Standard 2007. You enter the duration of each task. Then you assign multiple resources to each task. As a result, the duration of the tasks changes. You want the duration of all future tasks to automatically remain the same when you assign resources to those tasks. What should you do?
You need to convert this Excel task list into a project schedule in Microsoft Office Project Standard 2007
You want to reuse a task list created in Microsoft Office Excel 2003. You need to convert this Excel task list into a project schedule in Microsoft Office Project Standard 2007. What should you do?
You need to display all of this project information in one window
You are tracking a project in Microsoft Office Project Standard 2007. You monitor the project status by reviewing the following data: Actual start and finish datesScheduled start and finish datesCostsWork Task durations You need to display all of this project information in one window.
What should you do?
You need to ensure that the resources assigned to this task are scheduled to work during the night shift
You are creating a project schedule in Microsoft Office Project Standard 2007. One of the five project tasks can be worked on only at night. You need to ensure that the resources assigned to this task are scheduled to work during the night shift. What should you do?
What type of task should you set as the default?
In Microsoft Office Project Standard 2007, you create a project plan for managing one-hour meetings that are part of a project. For each meeting, you create one task with a resource assignment for each attendee. You need to ensure that all meeting tasks show that more work is required for meetings when additional resources attend. What type of task should you set as the default?
You need to update the schedule to reflect the new Resource B work estimate
You are tracking a project in Microsoft Office Project Standard 2007. Resources A and B are each assigned to work 40 hours on a task. After each resource works 30 hours, you update the schedule to reflect the actual work to date. Resource B estimates that she will need to work a total of 50 hours to complete her task assignment. You need to update the schedule to reflect the new Resource B work estimate. What should you do?
you need to display the planned cost totals for both resource groups
You are managing a project schedule in Microsoft Office Project Standard 2007. Your organization requires you to track planned costs for material and work resources. In the Resource Sheet view, you need to display the planned cost totals for both resource groups. What should you do?
you need to ensure that your project costs reflect the new hourly rate
You use Microsoft Office Project Standard 2007 to track your project schedule. You assign a resource to tasks scheduled during normal working hours. Starting the first of next month, the hourly rate of this resource will increase by 20 percent. Without changing any of the resource’s assignments, you need to ensure that your project costs reflect the new hourly rate. What should you do?