Exam 70-632: TS: Microsoft Office Project 2007, Managing Projects

What should you do?

You work from 8:00 A M. to 4:00 P.M. When scheduling projects in Microsoft Office Project Standard 2007, you set the working time of the project accordingly. When you create a new task, Project shows the finish time as 9:00 A M. on the following day. You need the finish time of new tasks to default to 4:00 P.M. What should you do?

What should you do?

In Microsoft Office Project Standard 2007, you create a task that includes 80 hours of work and has a duration of 10 days. You assign one resource at 100 percent with a standard rate of $100 per hour, resulting in an actual cost of $8,000. You set the baseline. You set the status date to a date that is later than the task finish date, and set the actual task finish date to the same date as the task finish date. The actual cost of work performed (ACWP) changes to $7,900. You need the ACWP to equal the actual cost. What should you do?


Page 17 of 17« First...10...1314151617