You need to model the dependency between the tasks without lead or lag time
You are creating a schedule in Microsoft Office Project Standard 2007. Task A starts before Task B, but is dependent on the schedule of Task B. You need to model the dependency between the tasks without lead or lag time. What should you do?
You need to keep track of how close the forecast completion dates of these deliverables are to their target da
Project team members are working on several of the tasks in your Microsoft Office Project Standard 2007 schedule in parallel. Each is of these tasks is represented by a summary task and a series of linked subtasks. You need to keep track of how close the forecast completion dates of these deliverables are to their target dates. What should you do?
You need to set up your project plan so that you can start tracking the costs
You are using Microsoft Office Project Professional 2007 to plan a project. The project has a fixed budget. You will use the budget-tracking feature to track the project costs against the budget. You need to set up your project plan so that you can start tracking the costs. What should you do first?
You need to estimate the potential variance before you set a baseline
You are building a schedule for an upcoming project in Microsoft Office Project Standard 2007. You must report the potential schedule variance to the stakeholders before they will approve the project. You need to estimate the potential variance before you set a baseline. What should you do?
You need to make Task B start two days later than it currently does
You are working on a schedule in Microsoft Office Project Standard 2007. There is one start-to-start dependency from Task A to Task B, and an As Soon As Possible constraint on Task B. You need to make Task B start two days later than it currently does. What should you do?
You need to schedule the task
You are adding a task to an existing project schedule in Microsoft Office Project Standard 2007. The task should start Tuesday, January 5 and must complete by Friday, January 8. You need to schedule the task. What should you do?
Which cost type should you use?
You are managing a project schedule in Microsoft Office Project Standard 2007. The project activities occur in two locations. Project team members must travel between the locations by air and incur lodging expenses. The travel occurs on an irregular schedule, and expenses have varying costs, frequencies, and durations. You need to model the costs in the schedule as accurately as possible.
Which cost type should you use?
You need to identify these tasks as critical
A project that you are tracking in Microsoft Office Project Standard 2007 has tight deadlines that must be met. For some tasks, a delay of more than 5 days will impact the project end date. You need to identify these tasks as critical. What should you do?
What should you display?
In Microsoft Office Project Standard 2007, you are tracking a project by duration. The Updating task status updates resource status option is not activated. You need to display the current status of the project. What should you display?
You need to compare the Gantt chart before and after the update within the same project plan
You are preparing to update the status of a baselined project plan in Microsoft Office Project Standard 2007. You need to compare the Gantt chart before and after the update within the same project plan. What should you do?