You need to put the tasks in the correct order
In Microsoft Office Project Standard 2007, you are creating a project plan from a list of serial tasks you have captured on paper. You have entered ten tasks in order and entered predecessors for all but the first task. You then notice that the eighth task should actually be between the fifth task and the sixth task. You need to put the tasks in the correct order. What should you do first?
You need to configure Project so that you can independently record the actual work and the actual duration
You are tracking a project in Microsoft Office Project Standard 2007. Assigned resources report status based on the actual work and the actual duration. You need to configure Project so that you can independently record the actual work and the actual duration. What should you do first?
You need to apply this fiscal year to all future projects by using the options
You use Microsoft Office Project Standard 2007 to manage project schedules. The fiscal year of your organization starts in July. You need to apply this fiscal year to all future projects by using the options. What should you do?
You need to restore the functionality in the files
You are opening old project schedule in Microsoft Office Project Standard 2007. The Project files have been customized to prompt you for your username before opening, so Project can log your actions. When you open the files, you notice that the prompt does not appear and logging does not take place. You need to restore the functionality in the files. What should you do?
What should you do?
You are tracking a project in Microsoft Office Project Standard 2007. A task in the project schedule is divided into two resource assignments. Each assignment will take 40 hours to complete. Resource A can begin the first week of the project. Resource B can begin 1 week later. You need the project schedule to reflect two resources with different start dates assigned to one task. What should you do?
What task type should you use?
You are tracking a project in Microsoft Office Project Standard 2007. When creating a task, you enter an estimated duration and assign one resource. The task might require additional effort and resources. You will make these changes as the scope of the task becomes clearer over the project lifecycle. You need to ensure that if you add resources to the task, work will increase. What task type should you use?
You need to create a task that reflects the resource restrictions so that you can efficiently track the estima
You are tracking a project in Microsoft Office Project Standard 2007. A resource can commit 2 hours of each 8-hour day to a task but cannot accurately estimate how long it will take him to complete the task. While working on the task, the resource will be better able to predict a completion date. You need to create a task that reflects the resource restrictions so that you can efficiently track the estimates to completion. What should you do?
you need to ensure that resources are not over-allocated, by using the method that gives you the most control
You are creating a project plan in Microsoft Office Project Standard 2007. Your organization does not allow resources to work overtime. Every time you make a change to your schedule, you need to ensure that resources are not over-allocated, by using the method that gives you the most control.
What should you do?
You need to set up the schedule to work around this resource’s non-standard availability
Your organization has a 5-day work week, with working hours from 8:00 A M. to 5:00 P.M. On a project that you track in Microsoft Office Project Standard 2007, a resource works different days on alternate weeks: Monday, Tuesday, and Friday in Week 1 and only Monday and Tuesday in Week 2. Each task on your schedule has a duration of at least 2 weeks. You need to set up the schedule to work around this resource’s non-standard availability. What should you do?
You need to ensure that your resources are not over-allocated regardless of the project end date
You are creating a project schedule in Microsoft Office Project Standard 2007. You assign multiple resources to each task, and estimate task durations for all project phases. You need to ensure that your resources are not over-allocated regardless of the project end date. What should you do?