You need to set the calendars correctly for this resources assignments
You are managing a project schedule in Microsoft Office Project Standard 2007. The calendar for one of your resources has been edited to block out his vacation days. You learn that the resource’s task can be performed only on certain days, and you create a calendar indicating those days. You need to set the calendars correctly for this resources assignments. What should you do?
You need to model this task correctly in the project schedule
You are managing a project schedule in Microsoft Office Project Standard 2007. Payment for a task is due on the first day of next month. The task can start any time after you receive the payment. You need to model this task correctly in the project schedule. What should you do?
You need to be able to display all tasks of all projects by phase
The project schedules you manage in Microsoft Office Project Standard 2007 all follow standard project lifecycle phases. You need to be able to display all tasks of all projects by phase. What should you do?
You need to order the tasks on a timeline so that you can analyze the critical path
You are using Microsoft Office Project Standard 2007 to create a project schedule in which you will be tracking the critical path of a set of linked tasks. When you add new tasks, their start dates default to the project start date. You need to order the tasks on a timeline so that you can analyze the critical path. What should you do?
Which type of dependency should you create?
You are creating a project schedule in Microsoft Office Project Standard 2007. Tasks A and B each have a projected duration of 10 days. You expect the actual duration of one or both tasks to change when work begins. You want Task B to start when Task A is 60 percent complete. You need to model these tasks in the project schedule by creating a dependency from Task A to Task B. Which type of dependency should you create?
You need to estimate the total project duration
You are managing a project schedule in Microsoft Office Project Standard 2007. You enter tasks and dependencies in the project schedule. The project is large and has multiple people working on deliverables at the same time. You need to estimate the total project duration. What should you do?
You need to align the project schedule data with the cost accounts
You are managing a project schedule in Microsoft Office Project Standard 2007. Your organization’s accounting system utilizes cost accounts to track expenses against revenue. You need to align the project schedule data with the cost accounts. What should you do?
You need to display the single critical path across all the projects
In Microsoft Office Project Standard 2007, you manage a program schedule that contains multiple individual project schedules. You need to display the single critical path across all the projects. What should you do?
You need to export the project milestone data from the project schedule to an Excel workbook for the purposes
You are managing the schedule for a multi-level project in Microsoft Office Project Standard 2007. The project is complete. There are a number of project milestones embedded at all levels of the project hierarchy. Your organization reports the names and finish dates of project milestones in a Microsoft Office Excel workbook. You need to export the project milestone data from the project schedule to an Excel workbook for the purposes of this report. What should you do?
You need to have Project calculate the latest possible start date based on the fixed completion date
You are creating a project in Microsoft Office Project Standard 2007. The project has a fixed completion date. You need to have Project calculate the latest possible start date based on the fixed completion date. What should you do?