Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
You have been tasked with creating a new application for ABC.com. You have been assigned a
team of developers, and a team of testers to achieve this. You have configured a build to run
automatically every night.
As a result of testers taking a long time to test and developers marking a large number of bugs as
“unable to reproduce”, you are required to make the test cycle time better.
Which of the following actions should you take?

Which of the following could be specified?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
You have been assigned to a development team that makes use of Scrum. You have been tasked
with measuring the impact of any process changes. To do this, you have to specify the necessary
key metrics.
Which of the following could be specified?

Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has a single Active Directory domain,
named ABC.com. The ABC.com network contains a Microsoft Visual Studio Team Foundation
Server (TFS) 2012 server.
You have been assigned to an internal development team as a technical team lead. The team
works in conjunction with a new external vendor on a project.
You have been instructed to make sure that the new external vendor supplies code of adequate
quality that corresponds to standards, and has no influence on production support.
Which of the following actions should you take?

Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
You have been tasked with developing a solution that allows for early user feedback, bug-free
software releases, and the most recent role specific best-of-breed tools.
Which of the following actions should you take?

Which of the following is an action you should also take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
ABC.com’s business analysts provide the development team with substantial, exceedingly
thorough requirements specifications. When certain business analysts complain that developers
are not meeting these requirements, you are instructed to make sure that requirements
management and delivery is strengthened.
You are planning to gather feedback from the business analysts on a regular basis using the

Feedback Manager tool.
Which of the following is an action you should also take?

Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
You have been assigned as the project manager of a new ABC.com application development
project. You are preparing to illustrate requirements for the project.
Which of the following actions should you take?

Which of the following can be ascertained by viewing this report?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
ABC.com is making use of Scrum as the process framework for new projects. You have opened
the Sprint Burndown report.

Which of the following can be ascertained by viewing this report? (Choose all that apply.)

Which of the following actions should you take NEXT?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
ABC.com has a number of developers working on various applications. You have been tasked
with putting an audit trail solution into operation to provide business analysts with an audit trail of
work item changes for all potential application releases.
You have enabled a check-in policy that requires a work item to be linked to the check-in.
Which of the following actions should you take NEXT?

Which of the following is another procedure that should be employed?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.

You are in the process of creating a new application that necessitates quick modifications once it
is moved into ABC.com’s production environment. You want to make sure that high quality is
encouraged by employing certain procedures. These procedures should also allow for the
maintainability of the code to be guaranteed.
Your strategy includes re-factoring code based on code metrics from the maintainability index, as
well as generating unit tests and examining code coverage.
Which of the following is another procedure that should be employed?

Which of the following actions should you take?

You are employed as a developer at ABC.com. ABC.com has ABC.com has a single Active
Directory domain, named ABC.com. ABC.com makes use of Microsoft Visual Studio 2012 for
development purposes.
You are the lead of the development team responsible for creating an application that includes a
number of automated builds. These builds are configured to perform the following:
•Build
•Execute code analysis.
•Unit test code segments.
You have been informed that documentation should be made available for quality checks, and
also the analysis for all alterations to the code base. Furthermore, you are instructed to guarantee
the quality of the code, as well as keep up the development team’s effectiveness.
Which of the following actions should you take?