Exam 70-332: Advanced Solutions of Microsoft SharePoint Server 2013 (update November 20th, 2016)

You need to meet the content recovery requirements for the farm

###BeginCaseStudy###
Topic 2, World Wide Importers
Background
General Background
Wide World Importers plans to upgrade from SharePoint 2010 to SharePoint 2013 to take advantage of
additional business intelligence (BI) services, including PerformancePoint Services, PowerPivot for Excel,
and SQL Server Reporting Services 2012 (SSRS). All users are members of an Active Directory Domain
Services (AD DS) domain.
Technical Background
The current environment integrates with a stand-alone instance of Microsoft SQL Server 2008 R2
Analysis Services (SSAS). Wide World Importers has acquired SQL Server 2012 licenses for the purpose of
upgrading all the SQL Server instances to SQL Server 2012.
Business Requirements
The SharePoint 2013 environment and supporting back-end servers that run SQL Server must be highly
available and redundant in the case of unplanned downtime or a disaster.
Technical Environment
SharePoint 2013 Production Farm Topology
The SharePoint 2013 production farm topology consists of the servers listed in the following table.

The Wide World Importers SharePoint 2013 environment has the following characteristics:
 A hardware load-balancer is configured to balance traffic between
PROD-WEB-01 and PROD-WEB-02.
 SSRS is installed on PROD-APP-01 in SharePoint integrated mode.
 SSRS report databases are stored on PROD-DB-01.
 A site collection named Report Center has been created at http://
reports.wideworldimporters.com.
 All SharePoint content and configuration databases are stored on PRODDB-01.
 All site collections have been migrated to a single content database
named WSS_Content.
 A content database named WSS_TempContent has been restored to
PROD-DB-01, but not attached to the SharePoint 2013 farm.
 An AD DS domain user account named PPS_SVC has been created.
SharePoint 2013 Disaster Recovery Site
The SharePoint 2013 Disaster Recovery farm topology consists of the servers listed in the following
table.

Technical Requirements
 Log shipping must be used to send transaction log backups to the
instance of SQL Server that is running in the disaster recovery site.
 Discrete sets of SharePoint content databases must be configured to
automatically failover together.
 An additional SQL Server 2012 Report Server must be added to the
SharePoint 2013 environment. The server must be configured to use SharePoint
integrated mode.
 Additional SQL Server 2012 Report Servers must not be installed on
machines that are running SharePoint as a front-end web server.
 Site Collection administrators must not have the ability to upgrade site
collections.
 Site Collection upgrade jobs must be throttled to a maximum of five site
collections at a time.
 A daily backup schedule must be created to perform SQL Server backups
of all SharePoint content and configuration databases. The PPS_SVC AD DS user account must be used for the
PerformancePoint service application.
 Farm administrators must be able to recover content from
WSS_TempContent without attaching the database to the farm.
 All content databases within the production farm must be set to readonly when patching and upgrading the farm.
 Farm administrators must be able to determine which sites were missed
or skipped during the upgrade process and must be able to monitor any future
upgrades.

###EndCaseStudy###

You need to meet the content recovery requirements for the farm.
What should you do?

You need to meet the content access requirements during the upgrade process

###BeginCaseStudy###
Topic 2, World Wide Importers
Background
General Background
Wide World Importers plans to upgrade from SharePoint 2010 to SharePoint 2013 to take advantage of
additional business intelligence (BI) services, including PerformancePoint Services, PowerPivot for Excel,
and SQL Server Reporting Services 2012 (SSRS). All users are members of an Active Directory Domain
Services (AD DS) domain.
Technical Background
The current environment integrates with a stand-alone instance of Microsoft SQL Server 2008 R2
Analysis Services (SSAS). Wide World Importers has acquired SQL Server 2012 licenses for the purpose of
upgrading all the SQL Server instances to SQL Server 2012.
Business Requirements
The SharePoint 2013 environment and supporting back-end servers that run SQL Server must be highly
available and redundant in the case of unplanned downtime or a disaster.
Technical Environment
SharePoint 2013 Production Farm Topology
The SharePoint 2013 production farm topology consists of the servers listed in the following table.

The Wide World Importers SharePoint 2013 environment has the following characteristics:
 A hardware load-balancer is configured to balance traffic between
PROD-WEB-01 and PROD-WEB-02.
 SSRS is installed on PROD-APP-01 in SharePoint integrated mode.
 SSRS report databases are stored on PROD-DB-01.
 A site collection named Report Center has been created at http://
reports.wideworldimporters.com.
 All SharePoint content and configuration databases are stored on PRODDB-01.
 All site collections have been migrated to a single content database
named WSS_Content.
 A content database named WSS_TempContent has been restored to
PROD-DB-01, but not attached to the SharePoint 2013 farm.
 An AD DS domain user account named PPS_SVC has been created.
SharePoint 2013 Disaster Recovery Site
The SharePoint 2013 Disaster Recovery farm topology consists of the servers listed in the following
table.

Technical Requirements
 Log shipping must be used to send transaction log backups to the
instance of SQL Server that is running in the disaster recovery site.
 Discrete sets of SharePoint content databases must be configured to
automatically failover together.
 An additional SQL Server 2012 Report Server must be added to the
SharePoint 2013 environment. The server must be configured to use SharePoint
integrated mode.
 Additional SQL Server 2012 Report Servers must not be installed on
machines that are running SharePoint as a front-end web server.
 Site Collection administrators must not have the ability to upgrade site
collections.
 Site Collection upgrade jobs must be throttled to a maximum of five site
collections at a time.
 A daily backup schedule must be created to perform SQL Server backups
of all SharePoint content and configuration databases. The PPS_SVC AD DS user account must be used for the
PerformancePoint service application.
 Farm administrators must be able to recover content from
WSS_TempContent without attaching the database to the farm.
 All content databases within the production farm must be set to readonly when patching and upgrading the farm.
 Farm administrators must be able to determine which sites were missed
or skipped during the upgrade process and must be able to monitor any future
upgrades.

###EndCaseStudy###

DRAG DROP
You need to meet the content access requirements during the upgrade process.
What should you do? (To answer, drag the appropriate terms to the correct location or locations in the
answer area. Each term may be used once, more than once, or not at all. You may need to drag the split
bar between panes or scroll to view content.)

You need to meet the disaster recovery requirements

###BeginCaseStudy###
Topic 2, World Wide Importers
Background
General Background
Wide World Importers plans to upgrade from SharePoint 2010 to SharePoint 2013 to take advantage of
additional business intelligence (BI) services, including PerformancePoint Services, PowerPivot for Excel,
and SQL Server Reporting Services 2012 (SSRS). All users are members of an Active Directory Domain
Services (AD DS) domain.
Technical Background
The current environment integrates with a stand-alone instance of Microsoft SQL Server 2008 R2
Analysis Services (SSAS). Wide World Importers has acquired SQL Server 2012 licenses for the purpose of
upgrading all the SQL Server instances to SQL Server 2012.
Business Requirements
The SharePoint 2013 environment and supporting back-end servers that run SQL Server must be highly
available and redundant in the case of unplanned downtime or a disaster.
Technical Environment
SharePoint 2013 Production Farm Topology
The SharePoint 2013 production farm topology consists of the servers listed in the following table.

The Wide World Importers SharePoint 2013 environment has the following characteristics:
 A hardware load-balancer is configured to balance traffic between
PROD-WEB-01 and PROD-WEB-02.
 SSRS is installed on PROD-APP-01 in SharePoint integrated mode.
 SSRS report databases are stored on PROD-DB-01.
 A site collection named Report Center has been created at http://
reports.wideworldimporters.com.
 All SharePoint content and configuration databases are stored on PRODDB-01.
 All site collections have been migrated to a single content database
named WSS_Content.
 A content database named WSS_TempContent has been restored to
PROD-DB-01, but not attached to the SharePoint 2013 farm.
 An AD DS domain user account named PPS_SVC has been created.
SharePoint 2013 Disaster Recovery Site
The SharePoint 2013 Disaster Recovery farm topology consists of the servers listed in the following
table.

Technical Requirements
 Log shipping must be used to send transaction log backups to the
instance of SQL Server that is running in the disaster recovery site.
 Discrete sets of SharePoint content databases must be configured to
automatically failover together.
 An additional SQL Server 2012 Report Server must be added to the
SharePoint 2013 environment. The server must be configured to use SharePoint
integrated mode.
 Additional SQL Server 2012 Report Servers must not be installed on
machines that are running SharePoint as a front-end web server.
 Site Collection administrators must not have the ability to upgrade site
collections.
 Site Collection upgrade jobs must be throttled to a maximum of five site
collections at a time.
 A daily backup schedule must be created to perform SQL Server backups
of all SharePoint content and configuration databases. The PPS_SVC AD DS user account must be used for the
PerformancePoint service application.
 Farm administrators must be able to recover content from
WSS_TempContent without attaching the database to the farm.
 All content databases within the production farm must be set to readonly when patching and upgrading the farm.
 Farm administrators must be able to determine which sites were missed
or skipped during the upgrade process and must be able to monitor any future
upgrades.

###EndCaseStudy###

DRAG DROP
You need to meet the disaster recovery requirements.
What should you do? (To answer, drag the appropriate terms to the correct location or locations in the
answer area. Each term may be used once, more than once, or not at all. You may need to drag the split
bar between panes or scroll to view content.)

You need to meet the technical requirements for failover

###BeginCaseStudy###
Topic 2, World Wide Importers
Background
General Background
Wide World Importers plans to upgrade from SharePoint 2010 to SharePoint 2013 to take advantage of
additional business intelligence (BI) services, including PerformancePoint Services, PowerPivot for Excel,
and SQL Server Reporting Services 2012 (SSRS). All users are members of an Active Directory Domain
Services (AD DS) domain.
Technical Background
The current environment integrates with a stand-alone instance of Microsoft SQL Server 2008 R2
Analysis Services (SSAS). Wide World Importers has acquired SQL Server 2012 licenses for the purpose of
upgrading all the SQL Server instances to SQL Server 2012.
Business Requirements
The SharePoint 2013 environment and supporting back-end servers that run SQL Server must be highly
available and redundant in the case of unplanned downtime or a disaster.
Technical Environment
SharePoint 2013 Production Farm Topology
The SharePoint 2013 production farm topology consists of the servers listed in the following table.

The Wide World Importers SharePoint 2013 environment has the following characteristics:
 A hardware load-balancer is configured to balance traffic between
PROD-WEB-01 and PROD-WEB-02.
 SSRS is installed on PROD-APP-01 in SharePoint integrated mode.
 SSRS report databases are stored on PROD-DB-01.
 A site collection named Report Center has been created at http://
reports.wideworldimporters.com.
 All SharePoint content and configuration databases are stored on PRODDB-01.
 All site collections have been migrated to a single content database
named WSS_Content.
 A content database named WSS_TempContent has been restored to
PROD-DB-01, but not attached to the SharePoint 2013 farm.
 An AD DS domain user account named PPS_SVC has been created.
SharePoint 2013 Disaster Recovery Site
The SharePoint 2013 Disaster Recovery farm topology consists of the servers listed in the following
table.

Technical Requirements
 Log shipping must be used to send transaction log backups to the
instance of SQL Server that is running in the disaster recovery site.
 Discrete sets of SharePoint content databases must be configured to
automatically failover together.
 An additional SQL Server 2012 Report Server must be added to the
SharePoint 2013 environment. The server must be configured to use SharePoint
integrated mode.
 Additional SQL Server 2012 Report Servers must not be installed on
machines that are running SharePoint as a front-end web server.
 Site Collection administrators must not have the ability to upgrade site
collections.
 Site Collection upgrade jobs must be throttled to a maximum of five site
collections at a time.
 A daily backup schedule must be created to perform SQL Server backups
of all SharePoint content and configuration databases. The PPS_SVC AD DS user account must be used for the
PerformancePoint service application.
 Farm administrators must be able to recover content from
WSS_TempContent without attaching the database to the farm.
 All content databases within the production farm must be set to readonly when patching and upgrading the farm.
 Farm administrators must be able to determine which sites were missed
or skipped during the upgrade process and must be able to monitor any future
upgrades.

###EndCaseStudy###

You need to meet the technical requirements for failover.
What should you do?

You need to implement a Reporting Services solution

###BeginCaseStudy###
Topic 2, World Wide Importers
Background
General Background
Wide World Importers plans to upgrade from SharePoint 2010 to SharePoint 2013 to take advantage of
additional business intelligence (BI) services, including PerformancePoint Services, PowerPivot for Excel,
and SQL Server Reporting Services 2012 (SSRS). All users are members of an Active Directory Domain
Services (AD DS) domain.
Technical Background
The current environment integrates with a stand-alone instance of Microsoft SQL Server 2008 R2
Analysis Services (SSAS). Wide World Importers has acquired SQL Server 2012 licenses for the purpose of
upgrading all the SQL Server instances to SQL Server 2012.
Business Requirements
The SharePoint 2013 environment and supporting back-end servers that run SQL Server must be highly
available and redundant in the case of unplanned downtime or a disaster.
Technical Environment
SharePoint 2013 Production Farm Topology
The SharePoint 2013 production farm topology consists of the servers listed in the following table.

The Wide World Importers SharePoint 2013 environment has the following characteristics:
 A hardware load-balancer is configured to balance traffic between
PROD-WEB-01 and PROD-WEB-02.
 SSRS is installed on PROD-APP-01 in SharePoint integrated mode.
 SSRS report databases are stored on PROD-DB-01.
 A site collection named Report Center has been created at http://
reports.wideworldimporters.com.
 All SharePoint content and configuration databases are stored on PRODDB-01.
 All site collections have been migrated to a single content database
named WSS_Content.
 A content database named WSS_TempContent has been restored to
PROD-DB-01, but not attached to the SharePoint 2013 farm.
 An AD DS domain user account named PPS_SVC has been created.
SharePoint 2013 Disaster Recovery Site
The SharePoint 2013 Disaster Recovery farm topology consists of the servers listed in the following
table.

Technical Requirements
 Log shipping must be used to send transaction log backups to the
instance of SQL Server that is running in the disaster recovery site.
 Discrete sets of SharePoint content databases must be configured to
automatically failover together.
 An additional SQL Server 2012 Report Server must be added to the
SharePoint 2013 environment. The server must be configured to use SharePoint
integrated mode.
 Additional SQL Server 2012 Report Servers must not be installed on
machines that are running SharePoint as a front-end web server.
 Site Collection administrators must not have the ability to upgrade site
collections.
 Site Collection upgrade jobs must be throttled to a maximum of five site
collections at a time.
 A daily backup schedule must be created to perform SQL Server backups
of all SharePoint content and configuration databases. The PPS_SVC AD DS user account must be used for the
PerformancePoint service application.
 Farm administrators must be able to recover content from
WSS_TempContent without attaching the database to the farm.
 All content databases within the production farm must be set to readonly when patching and upgrading the farm.
 Farm administrators must be able to determine which sites were missed
or skipped during the upgrade process and must be able to monitor any future
upgrades.

###EndCaseStudy###

You need to implement a Reporting Services solution.
What should you do?

Which two Windows PowerShell cmdlets should you perform?

###BeginCaseStudy###
Topic 2, World Wide Importers
Background
General Background
Wide World Importers plans to upgrade from SharePoint 2010 to SharePoint 2013 to take advantage of
additional business intelligence (BI) services, including PerformancePoint Services, PowerPivot for Excel,
and SQL Server Reporting Services 2012 (SSRS). All users are members of an Active Directory Domain
Services (AD DS) domain.
Technical Background
The current environment integrates with a stand-alone instance of Microsoft SQL Server 2008 R2
Analysis Services (SSAS). Wide World Importers has acquired SQL Server 2012 licenses for the purpose of
upgrading all the SQL Server instances to SQL Server 2012.
Business Requirements
The SharePoint 2013 environment and supporting back-end servers that run SQL Server must be highly
available and redundant in the case of unplanned downtime or a disaster.
Technical Environment
SharePoint 2013 Production Farm Topology
The SharePoint 2013 production farm topology consists of the servers listed in the following table.

The Wide World Importers SharePoint 2013 environment has the following characteristics:
 A hardware load-balancer is configured to balance traffic between
PROD-WEB-01 and PROD-WEB-02.
 SSRS is installed on PROD-APP-01 in SharePoint integrated mode.
 SSRS report databases are stored on PROD-DB-01.
 A site collection named Report Center has been created at http://
reports.wideworldimporters.com.
 All SharePoint content and configuration databases are stored on PRODDB-01.
 All site collections have been migrated to a single content database
named WSS_Content.
 A content database named WSS_TempContent has been restored to
PROD-DB-01, but not attached to the SharePoint 2013 farm.
 An AD DS domain user account named PPS_SVC has been created.
SharePoint 2013 Disaster Recovery Site
The SharePoint 2013 Disaster Recovery farm topology consists of the servers listed in the following
table.

Technical Requirements
 Log shipping must be used to send transaction log backups to the
instance of SQL Server that is running in the disaster recovery site.
 Discrete sets of SharePoint content databases must be configured to
automatically failover together.
 An additional SQL Server 2012 Report Server must be added to the
SharePoint 2013 environment. The server must be configured to use SharePoint
integrated mode.
 Additional SQL Server 2012 Report Servers must not be installed on
machines that are running SharePoint as a front-end web server.
 Site Collection administrators must not have the ability to upgrade site
collections.
 Site Collection upgrade jobs must be throttled to a maximum of five site
collections at a time.
 A daily backup schedule must be created to perform SQL Server backups
of all SharePoint content and configuration databases. The PPS_SVC AD DS user account must be used for the
PerformancePoint service application.
 Farm administrators must be able to recover content from
WSS_TempContent without attaching the database to the farm.
 All content databases within the production farm must be set to readonly when patching and upgrading the farm.
 Farm administrators must be able to determine which sites were missed
or skipped during the upgrade process and must be able to monitor any future
upgrades.

###EndCaseStudy###

You need to meet the security requirement for site collection upgrades.
Which two Windows PowerShell cmdlets should you perform? (Each correct answer presents part of the
solution. Choose two.)

You need to meet the database backup requirements.

###BeginCaseStudy###
Topic 2, World Wide Importers
Background
General Background
Wide World Importers plans to upgrade from SharePoint 2010 to SharePoint 2013 to take advantage of
additional business intelligence (BI) services, including PerformancePoint Services, PowerPivot for Excel,
and SQL Server Reporting Services 2012 (SSRS). All users are members of an Active Directory Domain
Services (AD DS) domain.
Technical Background
The current environment integrates with a stand-alone instance of Microsoft SQL Server 2008 R2
Analysis Services (SSAS). Wide World Importers has acquired SQL Server 2012 licenses for the purpose of
upgrading all the SQL Server instances to SQL Server 2012.
Business Requirements
The SharePoint 2013 environment and supporting back-end servers that run SQL Server must be highly
available and redundant in the case of unplanned downtime or a disaster.
Technical Environment
SharePoint 2013 Production Farm Topology
The SharePoint 2013 production farm topology consists of the servers listed in the following table.

The Wide World Importers SharePoint 2013 environment has the following characteristics:
 A hardware load-balancer is configured to balance traffic between
PROD-WEB-01 and PROD-WEB-02.
 SSRS is installed on PROD-APP-01 in SharePoint integrated mode.
 SSRS report databases are stored on PROD-DB-01.
 A site collection named Report Center has been created at http://
reports.wideworldimporters.com.
 All SharePoint content and configuration databases are stored on PRODDB-01.
 All site collections have been migrated to a single content database
named WSS_Content.
 A content database named WSS_TempContent has been restored to
PROD-DB-01, but not attached to the SharePoint 2013 farm.
 An AD DS domain user account named PPS_SVC has been created.
SharePoint 2013 Disaster Recovery Site
The SharePoint 2013 Disaster Recovery farm topology consists of the servers listed in the following
table.

Technical Requirements
 Log shipping must be used to send transaction log backups to the
instance of SQL Server that is running in the disaster recovery site.
 Discrete sets of SharePoint content databases must be configured to
automatically failover together.
 An additional SQL Server 2012 Report Server must be added to the
SharePoint 2013 environment. The server must be configured to use SharePoint
integrated mode.
 Additional SQL Server 2012 Report Servers must not be installed on
machines that are running SharePoint as a front-end web server.
 Site Collection administrators must not have the ability to upgrade site
collections.
 Site Collection upgrade jobs must be throttled to a maximum of five site
collections at a time.
 A daily backup schedule must be created to perform SQL Server backups
of all SharePoint content and configuration databases. The PPS_SVC AD DS user account must be used for the
PerformancePoint service application.
 Farm administrators must be able to recover content from
WSS_TempContent without attaching the database to the farm.
 All content databases within the production farm must be set to readonly when patching and upgrading the farm.
 Farm administrators must be able to determine which sites were missed
or skipped during the upgrade process and must be able to monitor any future
upgrades.

###EndCaseStudy###

DRAG DROP
You need to meet the database backup requirements.What should you do? (To answer, drag the appropriate terms to the correct location or locations in the
answer area. Each term may be used once, more than once, or not at all. You may need to drag the split
bar between panes or scroll to view content.)

Which type of storage solution should you implement?

###BeginCaseStudy###
Topic 3, Baldwin Museum of Science
Background
Baldwin Museum of Science has an Active Directory Domain Services (AD DS) domain named
BaldwinMuseumOfScience.com.
The domain has a SharePoint environment that contains two farms named ContentFarm and
SearchFarm.
ContentFarm includes content and collaboration tools. A custom app named Time Entry is deployed to
the App Store on ContentFarm. ContentFarm includes a site collection named HR.
You are planning for a major content and configuration update to the term store in the managed
metadata service application that is located on ContentFarm.
SearchFarm is reserved for crawling content and responding to search queries.
ContentFarm Topology
The topology of ContentFarm is shown in the following table.

ContentFarm has the following characteristics:
 Primary content for the farm is available at the URL
SharePoint.BaldwinMuseumOfScience.com.
 Requests for content from the farm are load-balanced between SPCWEB01 and SPC-WEB02. The servers that run Microsoft SQL Server are members of an
active/passive cluster that run a failover cluster named SP-SQL01.
 MySites sites for each user are hosted on a separate web application
available at the URL my.baldwinmuseumofscience.com.
 Requests for MySites pages are load-balanced between SPC-WEB01 and
SPC-WEB02.
 A full backup of the farm is performed once a week.
 An incremental backup of the farm is performed once a day.
 The Site Owner of the HR site collection requires that the HR Site
Collection be backed up in full on a daily basis.
 The managed metadata, user profile, and BCS service applications are
enabled in the farm.
 All members of the SharePoint developer team belong to an AD DS
security group named SharePoint_App_Dev.
SearchFarm Topology
The topology of SearchFarm is shown in the following table.

SearchFarm has the following characteristics:
 The farm currently uses SPS-DB01 as its primary database instance.
 SPS-DB01 has experienced multiple hard drive failures in the last month.
 The identity of the search service application is not documented.
Technical RequirementsThe following requirements must be met for ContentFarm and SearchFarm:
 All administrative activities must be performed by using Windows
PowerShell.
 Custom applications created by using the SharePoint app model must
be deployed to, and hosted in, an internal App Store.
 Site owners must not be able to directly purchase third-party apps from
the public SharePoint Store.
 Members of the SharePoint_App AD DS security group must have the
ability to submit new apps and app updates to the App Store of ContentFarm.
 Members of the SharePoint_App_Dev AD DS security group must not be
granted farm administrator rights in ContentFarm.
 The Time Entry app must remain available to users at all times.
 The contents of ContentFarm must be indexed by the Search service
application of SearchFarm.
 All responses to queries submitted by users in ContentFarm must be
served by the Search service application of SearchFarm.
 The database resources for SearchFarm must be configured to be highly
available by using SQL Server database mirroring with automatic failover.
 MySite content databases must be moved to a separate clustered
database instance. The new clustered database instance must be created by
using existing database servers in ContentFarm.
 All storage resources for both farms must be redundant and provide
high performance for both read and write operations and support disk
mirroring.
 A snapshot of the current state of the managed metadata service
application must be taken before the service application receives the planned
major update.

###EndCaseStudy###

You need to configure SPS-DB01.
Which type of storage solution should you implement?

You need to back up the HR site collection

###BeginCaseStudy###
Topic 3, Baldwin Museum of Science
Background
Baldwin Museum of Science has an Active Directory Domain Services (AD DS) domain named
BaldwinMuseumOfScience.com.
The domain has a SharePoint environment that contains two farms named ContentFarm and
SearchFarm.
ContentFarm includes content and collaboration tools. A custom app named Time Entry is deployed to
the App Store on ContentFarm. ContentFarm includes a site collection named HR.
You are planning for a major content and configuration update to the term store in the managed
metadata service application that is located on ContentFarm.
SearchFarm is reserved for crawling content and responding to search queries.
ContentFarm Topology
The topology of ContentFarm is shown in the following table.

ContentFarm has the following characteristics:
 Primary content for the farm is available at the URL
SharePoint.BaldwinMuseumOfScience.com.
 Requests for content from the farm are load-balanced between SPCWEB01 and SPC-WEB02. The servers that run Microsoft SQL Server are members of an
active/passive cluster that run a failover cluster named SP-SQL01.
 MySites sites for each user are hosted on a separate web application
available at the URL my.baldwinmuseumofscience.com.
 Requests for MySites pages are load-balanced between SPC-WEB01 and
SPC-WEB02.
 A full backup of the farm is performed once a week.
 An incremental backup of the farm is performed once a day.
 The Site Owner of the HR site collection requires that the HR Site
Collection be backed up in full on a daily basis.
 The managed metadata, user profile, and BCS service applications are
enabled in the farm.
 All members of the SharePoint developer team belong to an AD DS
security group named SharePoint_App_Dev.
SearchFarm Topology
The topology of SearchFarm is shown in the following table.

SearchFarm has the following characteristics:
 The farm currently uses SPS-DB01 as its primary database instance.
 SPS-DB01 has experienced multiple hard drive failures in the last month.
 The identity of the search service application is not documented.
Technical RequirementsThe following requirements must be met for ContentFarm and SearchFarm:
 All administrative activities must be performed by using Windows
PowerShell.
 Custom applications created by using the SharePoint app model must
be deployed to, and hosted in, an internal App Store.
 Site owners must not be able to directly purchase third-party apps from
the public SharePoint Store.
 Members of the SharePoint_App AD DS security group must have the
ability to submit new apps and app updates to the App Store of ContentFarm.
 Members of the SharePoint_App_Dev AD DS security group must not be
granted farm administrator rights in ContentFarm.
 The Time Entry app must remain available to users at all times.
 The contents of ContentFarm must be indexed by the Search service
application of SearchFarm.
 All responses to queries submitted by users in ContentFarm must be
served by the Search service application of SearchFarm.
 The database resources for SearchFarm must be configured to be highly
available by using SQL Server database mirroring with automatic failover.
 MySite content databases must be moved to a separate clustered
database instance. The new clustered database instance must be created by
using existing database servers in ContentFarm.
 All storage resources for both farms must be redundant and provide
high performance for both read and write operations and support disk
mirroring.
 A snapshot of the current state of the managed metadata service
application must be taken before the service application receives the planned
major update.

###EndCaseStudy###

HOTSPOT
You need to back up the HR site collection.
What should you do? (To answer, select the appropriate option from each drop-down list in the answer
area.)

You need to reconfigure the ContentFarm database topology

###BeginCaseStudy###
Topic 3, Baldwin Museum of Science
Background
Baldwin Museum of Science has an Active Directory Domain Services (AD DS) domain named
BaldwinMuseumOfScience.com.
The domain has a SharePoint environment that contains two farms named ContentFarm and
SearchFarm.
ContentFarm includes content and collaboration tools. A custom app named Time Entry is deployed to
the App Store on ContentFarm. ContentFarm includes a site collection named HR.
You are planning for a major content and configuration update to the term store in the managed
metadata service application that is located on ContentFarm.
SearchFarm is reserved for crawling content and responding to search queries.
ContentFarm Topology
The topology of ContentFarm is shown in the following table.

ContentFarm has the following characteristics:
 Primary content for the farm is available at the URL
SharePoint.BaldwinMuseumOfScience.com.
 Requests for content from the farm are load-balanced between SPCWEB01 and SPC-WEB02. The servers that run Microsoft SQL Server are members of an
active/passive cluster that run a failover cluster named SP-SQL01.
 MySites sites for each user are hosted on a separate web application
available at the URL my.baldwinmuseumofscience.com.
 Requests for MySites pages are load-balanced between SPC-WEB01 and
SPC-WEB02.
 A full backup of the farm is performed once a week.
 An incremental backup of the farm is performed once a day.
 The Site Owner of the HR site collection requires that the HR Site
Collection be backed up in full on a daily basis.
 The managed metadata, user profile, and BCS service applications are
enabled in the farm.
 All members of the SharePoint developer team belong to an AD DS
security group named SharePoint_App_Dev.
SearchFarm Topology
The topology of SearchFarm is shown in the following table.

SearchFarm has the following characteristics:
 The farm currently uses SPS-DB01 as its primary database instance.
 SPS-DB01 has experienced multiple hard drive failures in the last month.
 The identity of the search service application is not documented.
Technical RequirementsThe following requirements must be met for ContentFarm and SearchFarm:
 All administrative activities must be performed by using Windows
PowerShell.
 Custom applications created by using the SharePoint app model must
be deployed to, and hosted in, an internal App Store.
 Site owners must not be able to directly purchase third-party apps from
the public SharePoint Store.
 Members of the SharePoint_App AD DS security group must have the
ability to submit new apps and app updates to the App Store of ContentFarm.
 Members of the SharePoint_App_Dev AD DS security group must not be
granted farm administrator rights in ContentFarm.
 The Time Entry app must remain available to users at all times.
 The contents of ContentFarm must be indexed by the Search service
application of SearchFarm.
 All responses to queries submitted by users in ContentFarm must be
served by the Search service application of SearchFarm.
 The database resources for SearchFarm must be configured to be highly
available by using SQL Server database mirroring with automatic failover.
 MySite content databases must be moved to a separate clustered
database instance. The new clustered database instance must be created by
using existing database servers in ContentFarm.
 All storage resources for both farms must be redundant and provide
high performance for both read and write operations and support disk
mirroring.
 A snapshot of the current state of the managed metadata service
application must be taken before the service application receives the planned
major update.

###EndCaseStudy###

DRAG DROP
You need to reconfigure the ContentFarm database topology.
What should you do? (To answer, drag the appropriate options to the correct location or locations in the
answer area. Each option may be used once, more than once, or not at all. You may need to drag the
split bar between panes or scroll to view content.)


Page 2 of 1712345...10...Last »