What project component would you compare actual costs to in this instance?
Your project has a budget of $75,000 and is expected to last six months. Within your project, you are
forty percent complete and you have spent $35,000, and you want to compare the actual costs
against the earned value. What project component would you compare actual costs to in this
instance?
Which of the following virtual cubes contains the project risks and issues related information?
Which of the following virtual cubes contains the project risks and issues related information?
What is the best approach for completing this task?
You work as a Project Manager for Company Inc. You are using Microsoft Project Server and Project
Web Access to manage your projects. You need to work with your project team to create and
identify assignments for the current phase of your project. Within the project, there are several
assignments that no one in the project team is capable of completing because of time and resource
limitations. You would like to, for planning’s sake, assign someone to the assignment and then
replace the account with a contractor later. What is the best approach for completing this task?
What is the default policy setting for the anonymous user on a SharePoint site?
What is the default policy setting for the anonymous user on a SharePoint site?
How can she solve this problem?
You are the Microsoft Project Server administrator for your project. Diane, a project manager,
approaches you about her project. She needs help in assigning tasks to resources. Her project has 59
project team members, consisting of twenty general laborers, ten framers, ten electricians, five
plumbers, five carpenters, five general contractors, and four tile workers. She wants to create a way
to assign a task to these groups of resources rather than individuals within these groups of workers.
For example, she has a task in the project to “run CAT6 cable” that any electrician could complete.
How can she solve this problem?
What is the schedule performance index (SPI) of the project at the current point of time?
What is the primary requirement to create Data Analysis views for your organization?
You are the Microsoft Project Server administrator for your organization. Based on the requests of
several project managers and management, you need to create some Data Analysis views. What is
the primary requirement to create Data Analysis views for your organization?
What WSS Site group will Sally be a member of in order to have the Manage Windows SharePoint Team Services per
You are the project manager of the NHQ Project and are configuring your Microsoft Project Server,
SharePoint server and the project workspace for your project. One of your team members, Sally, will
also be serving as the administrator for the SharePoint Team Services. What WSS Site group will Sally
be a member of in order to have the Manage Windows SharePoint Team Services permissions in
Project Server?
Choose and reorder the steps to configure the domain controller in Project Server 2010.
What security setting can you use to configure the access so users can view the information on your SharePoint
You work as a project manager for TechWorld Inc. You are currently working on NHQ project in your
company. This project will replace an existing user software throughout the organization.
Management has asked you to configure the SharePoint Server so that all users throughout the
organization can view the content on your site. You want to make certain that the people who
access your SharePoint site are at least domain members. What security setting can you use to
configure the access so users can view the information on your SharePoint Server?