Which of the following actions will you perform to estimate the costs without assigning specific people to tas

You work as a Project Manager for Company Inc. You use Microsoft Office Project 2010 to develop the project schedule. You are assigned a project of remodeling a home. It requires electricians to work on multiple tasks. You have five electricians to work on your project, but you are not sure who will be the best for a certain task. Which of the following actions will you perform to estimate the costs without assigning specific people to tasks?

How will you manage the permissions on a project workspace directly without the permissions of the SharePoint

You work as a Project Server Administrator for Company Inc. You are assigned the task of testing the Project Web Access ability. You would like to manage the permissions on the project workspace sites without using the permissions of the SharePoint site. How will you manage the permissions on a project workspace directly without the permissions of the SharePoint site overriding your settings?


Page 7 of 16« First...56789...Last »