You need to display the status of all risks assigned to you in all projects
You are the manager of a set of projects that are saved to Microsoft Office Project Server 2007. Several risks are associated with these projects. You need to display the status of all risks assigned to you in all projects. What should you do?
You need to estimate the potential variance before you set a baseline
You are building a schedule for an upcoming project in Microsoft Office Project Standard 2007. You must report the potential schedule variance to the stakeholders before they will approve the project. You need to estimate the potential variance before you set a baseline. What should you do?
you need to receive a single weekly status report, while retaining the old monthly reports
You receive a status report from your project team on the first Monday of each month. You now want the team to provide a status report every Monday instead. In Microsoft Office Project Web Access, you need to receive a single weekly status report, while retaining the old monthly reports. What should you do?
You need to make Task B start two days later than it currently does
You are working on a schedule in Microsoft Office Project Standard 2007. There is one start-to-start dependency from Task A to Task B, and an As Soon As Possible constraint on Task B. You need to make Task B start two days later than it currently does. What should you do?
you need to create this view
You manage a set of projects that are saved to Microsoft Office Project Server 2007. You have been asked to generate a report for each project that displays the work performed by day and that can be filtered based on a customer custom field. In Microsoft Office Project Web Access, you need to create this view. What should you do?
You need to schedule the task
You are adding a task to an existing project schedule in Microsoft Office Project Standard 2007. The task should start Tuesday, January 5 and must complete by Friday, January 8. You need to schedule the task. What should you do?
you need to supply this report
You are tracking a set of projects that are saved to Microsoft Office Project Server 2007. Your organization’s directors have requested a weekly report displaying the progress of all active projects. They want to see cost and work grouped by a custom field for product. They cannot log on to Microsoft Office Project Web Access. In Project Web Access, you need to supply this report. What should you do?
Which cost type should you use?
You are managing a project schedule in Microsoft Office Project Standard 2007. The project activities occur in two locations. Project team members must travel between the locations by air and incur lodging expenses. The travel occurs on an irregular schedule, and expenses have varying costs, frequencies, and durations. You need to model the costs in the schedule as accurately as possible.
Which cost type should you use?
You need to ensure that another project manager can approve resource task updates while you are gone
In a project that is published to Microsoft Office Project Server 2007, your resources submit their progress updates to you for approval. You are leaving on vacation for 2 weeks.
You need to ensure that another project manager can approve resource task updates while you are gone.
What should you do?
You need to identify these tasks as critical
A project that you are tracking in Microsoft Office Project Standard 2007 has tight deadlines that must be met. For some tasks, a delay of more than 5 days will impact the project end date. You need to identify these tasks as critical. What should you do?