you need to examine all scheduled work for all project resources
You manage a portfolio of projects that are saved to Microsoft Office Project Server 2007. You are asked to provide detailed information about individual resource utilization on all tasks in all of your projects. Using Microsoft Office Project Web Access, you need to examine all scheduled work for all project resources. What should you do?
Which two actions should you perform? (Each correct answer presents part of the solution
You are managing a project schedule in Microsoft Office Project Standard 2007. The schedule includes tasks that require a variety of resources. You need to display only the tasks that use role- based resources, grouped by the resource to which they are assigned. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
you need to replace the old resource on all of his remaining scheduled work with the new resource
You manage a project that is published to Microsoft Office Project Server 2007. A resource has quit his job, and a replacement has been hired. In Microsoft Office Project Professional 2007, you need to replace the old resource on all of his remaining scheduled work with the new resource. What should you do?
Which view should you use?
You are assigning resources to a project in Microsoft Office Project Standard 2007. You allocate generic resources to a task and apply a work contour to some of the assignments. You need to view the assignments to verify that the work has been distributed correctly. Which view should you use?
You need to use a status report to record completion of the external task
In a project that is published to Microsoft Office Project Server 2007, some tasks are dependent on an external task. In Microsoft Office Project Web Access, you want to inform the relevant resources that they can begin their tasks. You need to use a status report to record completion of the external task. What should you do?
You need to provide the accountant with a different code that will meet her needs
You manage a project in Microsoft Office Project Standard 2007. The project is organized using Work Breakdown Structure (WBS) codes. Your organization’s accountant wants to be able to break down and group costs in a different manner. You need to provide the accountant with a different code that will meet her needs. What should you do?
You need to extract tabular information grouped by year, month, team, and resource
In Microsoft Office Project Web Access, you want to analyze the work performed on your projects over the last 2 years. You need to extract tabular information grouped by year, month, team, and resource. What should you do?
You need to have Project automatically reschedule Task A if Task B finishes earlier or later than scheduled
You are managing two projects in Microsoft Office Project Standard 2007. Task A in Project Alpha is dependent on Task B in Project Beta. You need to have Project automatically reschedule Task A if Task B finishes earlier or later than scheduled. What should you do?
You need to add some deliverables to your project tasks
You create and save a project schedule in Microsoft Office Project Professional 2007. You need to add some deliverables to your project tasks. However, the Manage Deliverables feature is not available. What should you do?
You need to identify the critical paths for the project
You are collaborating with a co-worker to create a project schedule in Microsoft Office Project Standard 2007. You are responsible for entering tasks in the first and last phases. Your co-worker will enter the tasks in the middle phase. You complete your work. There is a 45-day gap between the first phase and the last phase, in which there are no tasks or dependencies between phases. You need to identify the critical paths for the project. What should you do?