You need to update your project budget so that Project will automatically calculate future costs without requi

You are managing a project in Microsoft Office Project Standard 2007. The cost of a resource has increased. The resource is assigned to a task that is currently in progress. You need to update your project budget so that Project will automatically calculate future costs without requiring manual adjustments. What should you do?

What type of view should you create?

In a group of projects that are saved to Microsoft Office Project Server 2007, a custom field categorizes the projects by type. You are asked to create a view that displays a bar chart based on the type of project each resource has worked on for the past 2 years. You need to create a view in Microsoft Office Project Web Access so that you can generate this bar chart. What type of view should you create?

Which task type should you use?

You are tracking a project in Microsoft Office Project Standard 2007. You are updating a task that was originally estimated at 40 hours of work. The resource assigned to the task has worked 25 hours, and estimates she will require an additional 30 hours to complete the task. You update the actual work and remaining work. You need to configure the task so that it will update the assignment units when you enter the new data. Which task type should you use?

You need to put the tasks in the correct order

In Microsoft Office Project Standard 2007, you are creating a project plan from a list of serial tasks you have captured on paper. You have entered ten tasks in order and entered predecessors for all but the first task. You then notice that the eighth task should actually be between the fifth task and the sixth task. You need to put the tasks in the correct order. What should you do first?