You need to ensure that another project manager can approve resource task updates while you are gone
In a project that is published to Microsoft Office Project Server 2007, your resources submit their progress updates to you for approval. You are leaving on vacation for 2 weeks.
You need to ensure that another project manager can approve resource task updates while you are gone.
What should you do?
You need to ensure that Project issues a warning if you use resources that are not in the shared resource pool
You create a shared resource pool in Microsoft Office Project Standard 2007. You are allowed to use only resources from the shared resource pool in your projects. You need to ensure that Project issues a warning if you use resources that are not in the shared resource pool. What should you do?
You need to record the hours you work on assigned tasks
You are assigned to tasks in projects and in non-project activities that are published to Microsoft Office Project Server 2007. You need to record the hours you work on assigned tasks. What should you do?
You need to share the Gantt chart displaying the final three months of the project with a colleague who does n
You are tracking a project of six months duration in Microsoft Office Project Standard 2007. You need to share the Gantt chart displaying the final three months of the project with a colleague who does not have access to Project. What should you do?
You need to link the two tasks so that Task B starts when Task A is complete
You are working in Microsoft Office Project Web Access on an activity plan in which Task A and Task B are not linked. However, Task B cannot start until Task A is complete. You need to link the two tasks so that Task B starts when Task A is complete. What should you do?
you need to record travel costs as timephased data
You are updating a project in Microsoft Office Project Standard 2007. Your company tracks travel costs as timephased data. You create a cost resource named Travel for travel expenses, and assign this resource to each phase of the project. You also create a budget resource named Travel Budget. Costs have not been incurred evenly over the duration of the tasks. With the project schedule displayed in the Task Usage view, you need to record travel costs as timephased data. What should you do?
you need to replace the old resource on all of his remaining scheduled work with the new resource
You manage a project that is published to Microsoft Office Project Server 2007. A resource has quit his job, and a replacement has been hired. In Microsoft Office Project Professional 2007, you need to replace the old resource on all of his remaining scheduled work with the new resource. What should you do?
What should you do?
You are starting a new project in Microsoft Office Project Standard 2007. As part of tracking this project, you will need to compare the original project schedule to the current project schedule in the default Tracking Gantt view. What should you do?
You need to record the hours you work on assigned tasks
You are assigned to tasks in projects and in non-project activities that are published to Microsoft Office Project Server 2007. You need to record the hours you work on assigned tasks. What should you do?
You need to dynamically display the % Work Complete field within the chart area of the Tracking Gantt view
You are displaying a project schedule in Microsoft Office Project Standard 2007. You need to dynamically display the % Work Complete field within the chart area of the Tracking Gantt view.
What should you do?