You need to reverse the error made by the internal resource
You are the project manager of the coffee maker project. You need to reverse the error made by the internal resource. What should you do first?
You need to export the project milestone data from the project schedule to an Excel workbook for the purposes
You are managing the schedule for a multi-level project in Microsoft Office Project Standard 2007. The project is complete. There are a number of project milestones embedded at all levels of the project hierarchy. Your organization reports the names and finish dates of project milestones in a Microsoft Office Excel workbook. You need to export the project milestone data from the project schedule to an Excel workbook for the purposes of this report. What should you do?
you need to track this risk for the new tasks
You manage a large-scale project that is saved to Microsoft Office Project Server 2007. Several tasks already have a risk associated with them. You are adding additional tasks that will also have this associated risk. In Microsoft Office Project Web Access, you need to track this risk for the new tasks. What should you do?
You need to have Project calculate the latest possible start date based on the fixed completion date
You are creating a project in Microsoft Office Project Standard 2007. The project has a fixed completion date. You need to have Project calculate the latest possible start date based on the fixed completion date. What should you do?
you need to update the task so that dependent tasks will be rescheduled
An activity plan that is published to Microsoft Office Project Server 2007 has a task scheduled to take 5 more days. The resource assigned to the task tells you that the task requires 2 more days, instead of 5 more days. In Microsoft Office Project Web Access, you need to update the task so that dependent tasks will be rescheduled. What should you do?
You need to save the tasks, durations, views, and formatting of the current project for reuse
You are managing a project in Microsoft Office Project Standard 2007. You will be managing similar projects in the future, and plan to reuse information from the current project. You need to save the tasks, durations, views, and formatting of the current project for reuse. What should you do?
you need to replace the generic resource assignments with named resource assignments that have the required sk
In a plan that is published to Microsoft Office Project Server 2007, you have assigned generic resources to the tasks based on required skills. In Microsoft Office Project Professional 2007, you need to replace the generic resource assignments with named resource assignments that have the required skills. What should you do?
You need to ensure that the project scheduling calculations reflect a 7
Resources in your organization work a 7.5-hour day. In Microsoft Office Project Standard 2007, you create a new calendar based on the Standard calendar. You set the new calendar as the project calendar. You need to ensure that the project scheduling calculations reflect a 7.5-hour working day.
What should you do?
you need to update the existing template without duplicating the template file
An error has been discovered related to a time estimate in a template that is saved to Microsoft Office Project Server 2007. Working in Microsoft Office Project Professional 2007, you need to update the existing template without duplicating the template file. What should you do?
Where should you look for it?
You are creating a project plan from one of the sample schedules that is built in to Microsoft Office Project Standard 2007. You need to locate the sample schedule. Where should you look for it?