Which action should be performed first?
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys computer images by utilizing Microsoft Deployment Toolkit (MDT) 2008. The Zero Touch Installation (ZTI) deployment method is utilized by the company. You are required to have the user state data preserved from a current administrated computer named C01 on order to restore the data on a new managed computer. Which action should be performed first?
You need to link the tasks in such a way that Task B can start any time after Task A starts
You are working in Microsoft Office Project Web Access on an activity plan. Task B must not start until after Task A has started. You need to link the tasks in such a way that Task B can start any time after Task A starts. What should you do?
You need to resolve Matt Hinks issue of data discrepancy in Microsoft Office Project Web Access views
You need to resolve Matt Hinks issue of data discrepancy in Microsoft Office Project Web Access views. What should you do?
You need to model this task correctly in the project schedule
You are managing a project schedule in Microsoft Office Project Standard 2007. Payment for a task is due on the first day of next month. The task can start any time after you receive the payment. You need to model this task correctly in the project schedule. What should you do?
So what action should you perform?
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company deploys computer images by using Microsoft Deployment Toolkit (MDT) 2008. There are 250 client computers in the company. These computers use an unreliable WAN connection to connect to the network. To meet the working needs, the company decides to have these client computers upgraded to Windows Vista. Since you are the technical support, the company assigns this task to you. So what action should you perform?
Where can you view availability of resources while you assign them to the project plan?
You assign resources to a project plan in Microsoft Office Project Professional 2007. Several times a day, other project managers are doing the same. You need to ensure that the resources are available before you assign them. Where can you view availability of resources while you assign them to the project plan?
You need to resolve the scheduling conflict associated with the Northwind2U program
You need to resolve the scheduling conflict associated with the Northwind2U program. What should you do?
You need to be able to display all tasks of all projects by phase
The project schedules you manage in Microsoft Office Project Standard 2007 all follow standard project lifecycle phases. You need to be able to display all tasks of all projects by phase. What should you do?
So what action should you perform? (choose more than one)
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Microsoft Systems Management Server (SMS) 2003 with Service Pack 2 (SP2) is used by the company. There is a computer named Client01 in the company. Windows XP SP2 is being run by Client01. You have Microsoft Deployment Toolkit (MDT) 2008 installed on Client01. You must be able to use MDT 2008 and SMS 2003 to deploy operating systems. So what action should you perform? (choose more than one)
you need to reschedule the task to take 5 days
A project plan is published to Microsoft Office Project Server 2007. A fixed work task that is scheduled to take 4 days will really take 5 days. Without changing the remaining work on the task, you need to reschedule the task to take 5 days. The revised task must still appear in Microsoft Office Project Web Access on the timesheets of the assigned resources. What should you do?