PrepAway - Latest Free Exam Questions & Answers

Author: seenagape

You need to increase the task duration to 4 days, and ensure that the effort associated with the task does not

You are managing a project schedule in Microsoft Office Project Standard 2007. You create a fixed units task with a duration of 2 days. You have not yet assigned resources to the task. You need to increase the task duration to 4 days, and ensure that the effort associated with the task does not change. What should you do?

So what action should you perform?

You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company has two locations. Now you are planning an infrastructure to have Windows Vista deployed in two locations. For the Dallas office, you intend to perform Lite Touch Installations (LTI) by using Microsoft Deployment Toolkit (MDT). For the San Francisco office, you intend to perform Zero Touch Installations (ZTI) with the use of MDT. Each office has been configured with its own Active Directory forest. In each location, you have to make preparation of the least required infrastructure for deployment. So what action should you perform?

you need to assign resources with specific skills to tasks, and then replace them with named resources

You create a project with a generic project team. The project is saved to Microsoft Office Project Server 2007. In Microsoft Office Project Professional 2007, you need to assign resources with specific skills to tasks, and then replace them with named resources. The named resources need to see their new assignments. What should you do?

What task type should you use?

You are managing a project schedule in Microsoft Office Project Standard 2007. You originally thought one resource could complete a task in 10 days. You now think it will take the full-time effort of two resources to complete the task by the original finish date. You need to ensure that when you add the second resource, Project maintains the original finish date. What task type should you use?

Which MDT 2008 deployment point should be used?

You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company offices reside in seven different locations. Now the company decides to have all the client computers deployed with Windows Vista images by using Microsoft Deployment Toolkit (MDT) and Systems Management Server (SMS) 2003. You have to use the Zero Touch Installation (ZTI) deployment method to perform the deployment of images. Which MDT 2008 deployment point should be used?

You need to submit the schedule tomorrow with this task allocated to two resources

The project you are creating in Microsoft Office Project Standard 2007 includes a task with definite deadlines. Completing the task work by the deadline requires two resources with specific skills. Only one resource with these skills is available. You need to submit the schedule tomorrow with this task allocated to two resources. What should you do?