You need to support the travel budget requirement
You need to support the travel budget requirement. What should you do first?
You need to save the tasks, durations, views, and formatting of the current project for reuse
You are managing a project in Microsoft Office Project Standard 2007. You will be managing similar projects in the future, and plan to reuse information from the current project. You need to save the tasks, durations, views, and formatting of the current project for reuse. What should you do?
From the following seven actions, which three should be performed to finish the task? (Choose more than one)
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. You deploy operating system images to your company’s computers by utilizing Microsoft Deployment Toolkit (MDT) 2008 to. Specific drivers should be assigned to a driver group. From the following seven actions, which three should be performed to finish the task? (Choose more than one)
you need to approve this time
In a project that is published to Microsoft Office Project Server 2007, your resources record their time as hours per project, instead of hours per task. In Microsoft Office Project Web Access, you need to approve this time. What should you do?
You need to support Dan Jumps notification requirements
You need to support Dan Jumps notification requirements. What should you do?
You need to ascertain whether the resource is overallocated during the first month of the schedule
You are developing a project schedule in Microsoft Office Project Standard 2007. The project uses a shared resource pool. One of the resources assigned to the project is assigned to another project on a half-time basis during the first month of the project. You need to ascertain whether the resource is overallocated during the first month of the schedule. What should you do first?
So what action should you perform?
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company is considering deploying Windows Vista with Service Pack 1 (SP1). The table below shows the management infrastructure. Deployments to server computers need to be monitored.
So what action should you perform?
You need to be able to record time spent on unplanned, non-project activities
Your organization tracks resource utilization using Microsoft Office Project Server 2007. Your project time is captured on the task level. You need to be able to record time spent on unplanned, non-project activities. What should you do?
You need to assign an existing member of the helmet design team to this task
A bike helmet design task scheduled for the month of March will take 40 hours to complete. You need to assign an existing member of the helmet design team to this task. What should you do?
You need to ensure that the task is completed in 5 days
You are creating a project plan in Microsoft Office Project Standard 2007. Your resources work 8 hours a day, 5 days a week. A fixed duration, effort-driven task with 80 hours of work has one resource assigned to it at 50%. The schedule changes, and the task now must be completed in 5 days. You need to ensure that the task is completed in 5 days. What should you do?