In the software package properties, which parameter or parameters should be included?
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company has the 2007 Microsoft Office system deployed to client computers by using System Center Configuration Manager 2007. For the network installation point, \\Server1\Office2007 is used by you. An installation of Office 2007 is customized and a new Office setup customization .msp file is created by using the Office Customization Tool (OCT). The .msp file is stored in the \\Server1\Office2007\Custom folder by you. The default Config.xml file is modified by you to have the required customizations included. In Configuration Manager 2007, you are creating a software package to deploy Office 2007. For the software package, the installation parameters should be specified. In the software package properties, which parameter or parameters should be included?
you need to propose these resource assignments so that senior management can review and approve them
You are developing a project that is published to Microsoft Office Project Server 2007. You have identified the resources you want to work on your project. In Microsoft Office Project Web Access, you need to propose these resource assignments so that senior management can review and approve them. What should you do?
You need to support the data-evaluation requirements of Amy Strande
You need to support the data-evaluation requirements of Amy Strande. What should you do?
You need to ascertain the late finish of Task 4
You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: You need to ascertain the late finish of Task 4. What is the result?
So what action should you perform?
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company perform the deployment of computer images by using Microsoft Deployment Toolkit (MDT) 2008. You are going to have the operating system on client computers on your network refreshed. For client computers, you have to group configuration settings by specific geographic region. So what action should you perform?
You need to display the differences between dates for program milestones and project milestones when they chan
In Microsoft Office Project Professional 2007, your program manager has created a program schedule with a Deliverables list representing key milestones. You need to display the differences between dates for program milestones and project milestones when they change. What should you do?
You need to provide David Pelton with the requested information regarding project schedule
You need to provide David Pelton with the requested information regarding project schedule.
What should you do?
Which dependency should you delete?
You are editing a schedule in Microsoft Office Project Standard 2007, scheduling from the start of the project. You notice that Task X is starting later than you expected. Task W is 100 percent complete. You need Task X to start on Tuesday. Which dependency should you delete?
So what should you do? (choose more than one)
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. There is a head office and two remote offices in your company. The head office is located in San Francisco. The two remote offices are respectively located in Dallas and Orlando. All of the three offices have 120 client computers. The table below shows the relevant portion of the network. For distributing a Windows Vista deployment image, a shared folder is created in San Francisco. In each office, there are image deployment technicaians. For having a image with 4-GB deployed, you have to prepare the environment in each office. In one night, technicians have to use the least possible administrative effort to have all client computers deployed with image. So what should you do? (choose more than one)
You need to incorporate the task updates of local resources into your plan so that you can analyze the progres
You are tracking a project that is published to Microsoft Office Project Server 2007. In the project plan, some of your resources are local. You need to incorporate the task updates of local resources into your plan so that you can analyze the progress made by each resource.
What should you do?