Which action should be performed?
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys the 2007 Microsoft Office system to client computers by utilizing Microsoft System Center Configuration Manager 2007. The installation of Office 2007 should be customized. In addition, the Office security settings should be defined during the installation.
Which action should be performed?
You need to link the two tasks so that Task B starts when Task A is complete
You are working in Microsoft Office Project Web Access on an activity plan in which Task A and Task B are not linked. However, Task B cannot start until Task A is complete. You need to link the two tasks so that Task B starts when Task A is complete. What should you do?
You need to implement the assignment process for John Morris
You need to implement the assignment process for John Morris. What should you do?
Which dependency should you create?
You take responsibility for tracking an existing schedule in Microsoft Office Project Standard 2007. The project schedule uses the default Standard calendar. There are no constraints on your project. You need to order computer equipment for your development environment. Your supplier will deliver the equipment three weeks after receiving a purchase order. You enter a milestone for the purchase order date and create an equipment installation task. You need to create a dependency from the purchase order task to the equipment installation task so you can schedule the equipment installation based on a specific purchase order date. Which dependency should you create?
Which action should be performed to achieve the goal?
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. There is a Windows Server 2003 Remote Installation Services (RIS) server, and the server is named Server01. You are making upgrading to Windows Deployment Services. There are current images, and the images are created by utilizing RIPREP. The existing images and Windows Vista images should be deployed to client computers. Which action should be performed to achieve the goal?
You need to display the status of all risks assigned to you in all projects
You are the manager of a set of projects that are saved to Microsoft Office Project Server 2007. Several risks are associated with these projects. You need to display the status of all risks assigned to you in all projects. What should you do?
Which type of resource should you create?
You need to help Chris Meyer create the Database Developers resource.
Which type of resource should you create?
You need to estimate the total cost of the project
You are building a project plan in Microsoft Office Project Standard 2007. You expand the project plan to display all outline levels and the project summary task. You enter resources and their costs. You have not yet set a baseline. You need to estimate the total cost of the project. What should you do?
From the following four folders, which one should you examine the log files in?
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys Windows Vista to client computers by utilizing Microsoft Deployment Toolkit (MDT) 2008. However, the company cannot deploy Windows Vista to a specific computer successfully. The log files should be examined to have the failed installation troubleshot. From the following four folders, which one should you examine the log files in?
You need to assign named resources without changing their availability in Microsoft Office Project Server 2007
You create a proposal in Microsoft Office Project Web Access. You want to publish the proposal, although resource assignments are not yet approved. You need to assign named resources without changing their availability in Microsoft Office Project Server 2007. What should you do?