Which action should be performed to achieve the goal?
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Windows Automated Installation Kit (Windows AIK) is utilized by you. You capture an image of a reference computer is captured, and Windows Vista with Service Pack 1 (SP1) is installed in the computer. You are required to confirm the data integrity of the image during deployment process. Which action should be performed to achieve the goal?
you need to track the fixed payment costs as they are incurred and include these payments in the project costs
You manage a project that is saved to Microsoft Office Project Server 2007.
Your organization will make fixed payments of $10,000 to a subcontractor as the organization approves each work product. Each work product requires multiple tasks. In Microsoft Office Project Web Access, you need to track the fixed payment costs as they are incurred and include these payments in the project costs. What should you do?
You need to manage access to resources and projects for departmental managers
You need to manage access to resources and projects for departmental managers. What should you do?
What should you do?
In Microsoft Office Project Standard 2007, you are tracking a project for which the overall duration might change. A resource who works 8 hours a day, 5 days a week, spends 2 hours a day creating reports for the project. You need the project schedule to reflect this estimated reporting work. What should you do?
Which action should be performed?
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. You deploy client computer images by utilizing Microsoft Deployment Toolkit (MDT) 2008 and Microsoft System Center Configuration Manager 2007. You company has created a Windows Vista deployment package for all the client computers. You try to have a Configuration Manager 2007 report run. However, the Run command is not displayed in the actions pane. You should be possible to utilize Configuration Manager Reports to run the report. Which action should be performed?
you need to track this risk for the new tasks
You manage a large-scale project that is saved to Microsoft Office Project Server 2007. Several tasks already have a risk associated with them. You are adding additional tasks that will also have this associated risk. In Microsoft Office Project Web Access, you need to track this risk for the new tasks. What should you do?
You need to create the program cost report as requested by the CEO
You need to create the program cost report as requested by the CEO. What should you do?
Which view should you use?
You are assigning resources to a project in Microsoft Office Project Standard 2007. You allocate generic resources to a task and apply a work contour to some of the assignments. You need to view the assignments to verify that the work has been distributed correctly. Which view should you use?
Which action should you perform?
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Microsoft System Center Configuration Manager 2007 is utilized by the company to have software deployed. Microsoft Deployment Toolkit (MDT) 2008 is installed. Remotely refreshment on a new custom operating system image to client computers should be enabled, and the requiring interaction should not occur during the installation. Which action should you perform?
you need to update the existing template without duplicating the template file
An error has been discovered related to a time estimate in a template that is saved to Microsoft Office Project Server 2007. Working in Microsoft Office Project Professional 2007, you need to update the existing template without duplicating the template file. What should you do?