You need to set up skills-based assignments according to company policy
You need to set up skills-based assignments according to company policy.
What should you do first?
you need to display the planned cost totals for both resource groups
You are managing a project schedule in Microsoft Office Project Standard 2007. Your organization requires you to track planned costs for material and work resources. In the Resource Sheet view, you need to display the planned cost totals for both resource groups. What should you do?
From the following four options, which two should be chosen to finish the task? (Choose more than one
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys computer images by utilizing Microsoft Deployment Toolkit (MDT) 2008 to. The Lite Touch Installation (LTI) deployment method is utilized by the company. A shared folder named Logs is created to have the deployment logs stored during the deployment process. You find a problem that during the deployment process, log files are not created. You can see the NTFS permissions for the Logs folder from the table listed below. You are required to make sure that during the deployment process, log files are created. From the following four options, which two should be chosen to finish the task? (Choose more than one.)
You need to check resource availability to ascertain how much free time the resources required for the new pro
You manage a portfolio of projects that are saved to Microsoft Office Project Server 2007. Your organization is evaluating whether to take on another project. A key factor in that decision is whether the necessary resources will be available during the next 3 months. Your organization’s resources include full-time and part-time regular employees and some contractors with variable schedules. You need to check resource availability to ascertain how much free time the resources required for the new project will have during the next 3 months. What should you do?
You need to include the requested variance reports for your client in the project plan
You need to include the requested variance reports for your client in the project plan. What should you do?
you need to ensure that your project costs reflect the new hourly rate
You use Microsoft Office Project Standard 2007 to track your project schedule. You assign a resource to tasks scheduled during normal working hours. Starting the first of next month, the hourly rate of this resource will increase by 20 percent. Without changing any of the resource’s assignments, you need to ensure that your project costs reflect the new hourly rate. What should you do?
Which action should be performed?
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. There is a server named Serevr01 in your company, and the server runs Microsoft Windows Server 2003 with Service Pack 1 (SP1). Microsoft Deployment Toolkit (MDT) 2008 is installed on Serevr01. The deployment infrastructure should be prepared to support multicast transmission of images.
Which action should be performed?
Where can you view availability of resources while you assign them to the project plan?
You assign resources to a project plan in Microsoft Office Project Professional 2007. Several times a day, other project managers are doing the same. You need to ensure that the resources are available before you assign them. Where can you view availability of resources while you assign them to the project plan?
You need to provide management with an earned value report for each project
You need to provide management with an earned value report for each project. What should you do?
What task type should you use?
You are managing a project schedule in Microsoft Office Project Standard 2007. A scheduled task requires 100 hours of work and has a duration of 10 days. One resource is available to do the work, but you might get another. You need to set up the task so that if you add another resource, the new resource will share the hours with the original resource and the finish date will remain the same.
What task type should you use?