You need to deliver the cost overrun view that Maria needs
You need to deliver the cost overrun view that Maria needs. What should you do?
What should you do?
You are creating a project schedule in Microsoft Office Project Standard 2007. You set the project start date to today and enter a task. You notice that the year shown in the project timescale does not match the date shown in the date field. You need the timescale to show the current year instead of the next year. What should you do?
What should you do?
You are creating a project schedule in Microsoft Office Project Standard 2007. You set the project start date to today and enter a task. You notice that the year shown in the project timescale does not match the date shown in the date field. You need the timescale to show the current year instead of the next year. What should you do?
Which action should be performed?
You work as an IT professional in an international corporation named Wiikigo. You are xperienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. You intend to deploy Windows Vista with Service Pack 1 (SP1) images by utilizing Microsoft Deployment Toolkit (MDT) 2008. In your company, the images will be deployed to the client computers. You intend to have the 2007 Microsoft Office system integrated into the imaging process. You are required to have Office 2007 installed on the client computers before the first log on for the users. The image should be kept as small as possible. Which action should be performed?
You need to find out how many and which deliverables are due each day for the next 2 months
Several projects that are published to Microsoft Office Project Server 2007 have many linked deliverables. You need to find out how many and which deliverables are due each day for the next 2 months. What should you do?
You need to provide the information requested by the risk manager
You need to provide the information requested by the risk manager. What should you do?
What should you do?
You are entering tasks in a project you are tracking in Microsoft Office Project Standard 2007. You enter the duration of each task. Then you assign multiple resources to each task. As a result, the duration of the tasks changes. You want the duration of all future tasks to automatically remain the same when you assign resources to those tasks. What should you do?
What should you do?
You are entering tasks in a project you are tracking in Microsoft Office Project Standard 2007. You enter the duration of each task. Then you assign multiple resources to each task. As a result, the duration of the tasks changes. You want the duration of all future tasks to automatically remain the same when you assign resources to those tasks. What should you do?
So what action should you perform to accomplish your task? (choose more than one)
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. On the corporate network, you manage operating system deployments by using Microsoft System Center Configuration Manager 2007 and Microsoft Deployment Toolkit (MDT) 2008. A new network is configured by you. This network is separated from the corporate network. According to the company requirement, computers on the new network should be deployed with a Windows Vista image. So what action should you perform to accomplish your task? (choose more than one)
You need to get a status report from your team
You are checking on the status of a project that is published to Microsoft Office Project Server 2007. You want more recent information than is available in the latest status report, but you dont want to wait for the next regularly scheduled status report. You need to get a status report from your team. What should you do?