In Project Web Access, what should you do?
You need to efficiently build a report that meets the requirements of the management team in the Mexico office. In Project Web Access, what should you do?
You need to ensure that the task finish dates calculate as they did prior to you modifying the calendar, while
The resources in your organization work a 7.5-hour day. In Microsoft Office Project Standard 2007, you create a new project calendar in an existing schedule, modifying the default work week to reflect these working hours. As a result of this modification, the finish dates of all the existing tasks in the schedule change. For example, a 1-day duration task that previously finished on the same day as it started now finishes on the next day. You need to ensure that the task finish dates calculate as they did prior to you modifying the calendar, while maintaining the 7.5-hour work day. What should you do?
You need to ensure that the task finish dates calculate as they did prior to you modifying the calendar, while
The resources in your organization work a 7.5-hour day. In Microsoft Office Project Standard 2007, you create a new project calendar in an existing schedule, modifying the default work week to reflect these working hours. As a result of this modification, the finish dates of all the existing tasks in the schedule change. For example, a 1-day duration task that previously finished on the same day as it started now finishes on the next day. You need to ensure that the task finish dates calculate as they did prior to you modifying the calendar, while maintaining the 7.5-hour work day. What should you do?
Which action should be performed to finish the task?
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys client computer images by utilizing Microsoft Deployment Toolkit (MDT) 2008. You are utilizing Lite Touch Installation (LTI) to configure MDT to deploy an image. You should be enabled to create a task sequence so as to have a previously captured image deployed successfully. Which action should be performed to finish the task?
you need to update the risk
You manage a project that is published to Microsoft Office Project Server 2007. A risk associated with your project has changed. Working on the project workspace site, you need to update the risk. What should you do?
You need to assist Maria with her report to the steering committee
You need to assist Maria with her report to the steering committee. What should you do with each project?
You need to save the new template without including completed work data from the existing project
Using Microsoft Office Project Standard 2007, you are creating a project template from an existing project. You need to save the new template without including completed work data from the existing project. What should you do?
You need to save the new template without including completed work data from the existing project
Using Microsoft Office Project Standard 2007, you are creating a project template from an existing project. You need to save the new template without including completed work data from the existing project. What should you do?
So what action should you perform to make sure of this?
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company deploys computer images by using Microsoft Deployment Toolkit (MDT) 2008. There is a server named S01. MDT is installed on S01. Task Sequencer is configured by you to run under the credentials of an Active Directory Domain Services (AD DS) account which is named Sequencer. There is a client computer named C1. C1 is a desktop computer. Task Sequencer is run by a user to execute tasks on C1. But an error message is sent to the user saying that access is disallowed. Since you are the technical support, you have to solve this problem, making sure that the user is able to execute tasks on C1 by using Task Sequencer. So what action should you perform to make sure of this?
You need to ensure that your timesheet matches the task updates
In a project that is published to Microsoft Office Project Server 2007, you have entered time against your tasks in your timesheet, but that time is not recorded in your task updates. You need to ensure that your timesheet matches the task updates. What should you do?