Which action should be performed first?

You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys computer images by utilizing Microsoft Deployment Toolkit (MDT) 2008. The Zero Touch Installation (ZTI) deployment method is utilized by the company. You are required to have the user state data preserved from a current administrated computer named C01 on order to restore the data on a new managed computer. Which action should be performed first?

You need to update the task so that it is listed as completed, without modifying the actual work

You publish a task assignment to a resource with 16 hours of work in Microsoft Office Project Server 2007. The resource updates the task with 8 hours of actual work. A note in the task tells you that the task is already completed despite the original estimate. You need to update the task so that it is listed as completed, without modifying the actual work. What should you do?

Which action should be performed?

You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Microsoft System Center Configuration Manager 2007 and Microsoft Deployment Toolkit (MDT) 2008 are installed in your company. 100 new computers are purchased by your company, and an operating system is not installed in the new computers. And you set Configuration Manager 2007 to deploy Windows Vista. An image should be deployed to each of the 100 new computers, and any type of bootable media should not be utilized. Which action should be performed?

So what action should you perform to achieve this?

You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. There are four images for you. On a server named S01, you use Microsoft Deployment Toolkit (MDT) 2008 to deploy these four images by using Microsoft Deployment Toolkit (MDT) 2008. There are also three additional images for you. On a server named S02, you use Windows Deployment Services to deploy the three additional images. S01 has no free space for new images. You must be able to use MDT to deploy the Windows Deployment Services images. So what action should you perform to achieve this?

Which MDT 2008 deployment point should be used?

You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company offices reside in seven different locations. Now the company decides to have all the client computers deployed with Windows Vista images by using Microsoft Deployment Toolkit (MDT) and Systems Management Server (SMS) 2003. You have to use the Zero Touch Installation (ZTI) deployment method to perform the deployment of images. Which MDT 2008 deployment point should be used?