You need to resolve this specific error

You are deploying Microsoft Office Project Server 2007. Your server and
software environment is configured as shown in the following table. You attempt to provision the Project Web Access (PWA) Web site. You receive the following error message: The Project Application Service doesnt exist or is stopped. Start the Project Application Service.

You need to resolve this specific error.

What should you do?

You need to synchronize the resource pools

Your Microsoft Office Project Server 2007 environment includes a Project Portfolio Server (PPS) 2007 computer named ServerA. You create an enterprise resource field that indicates resource competency. You attempt to synchronize resource pools. You receive the following error message: Could not synchronize resource pool from server ServerA. No custom field assigned to competencies. You need to synchronize the resource pools. What should you do?

You need to ensure that after the next synchronization the enterprise project field appears in PPS as a projec

Your Microsoft Office Project Server 2007 environment includes Project Portfolio Server (PPS) 2007. You create an enterprise project field in Project Web Access (PWA), and you populate the field for all projects. You need to ensure that after the next synchronization the enterprise project field appears in PPS as a project attribute. What should you do?