which of the following components of Microsoft Project Server architecture should these developers interact wi
You work as a Project Administrator for Company Inc. You are working with some developers who
want to create a third-party application to manipulate the Project Server business objects, such as
the calendars in projects. You are concerned about maintaining data integrity, as the developers
want to access the data in the Microsoft Project Server. To preserve data integrity, which of the
following components of Microsoft Project Server architecture should these developers interact with
rather than the project databases?
What will be the cost performance index (CPI) of the project at the current point of time?
You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance
efficiencies of a project. The related key values are provided in the table below:
MeasurementsValues
BCWP (or EV)325
BCWS (or PV) 300
ACWP (or AC)410
What will be the cost performance index (CPI) of the project at the current point of time?
Which of the following features of Project Server 2010 should be used by the project team?
You work as a Project Manager of the HHQ Project for your company. You are using the timesheets
feature of Microsoft Project Server and Project Web Access so that team members can record the
hours spent on their project work. This information is compiled and is used for project billing to the
customer. You have another project which is a fixed fee contract and you would not need to keep
track of hours spent on each task in the project. You want the team members to report their
percentage completion of assignments for project scheduling. Which of the following features of
Project Server 2010 should be used by the project team?
Which of the following Microsoft Project Server databases stores the configuration information for the WSS far
Which of the following Microsoft Project Server databases stores the configuration information for
the WSS farm?
How will you configure the email settings for an application?
You work as a Project Manager for Company Inc. Your current project is based on WSS and Microsoft
Project Server. You are using a Web application that the end user would like to monitor. The Web
application can be configured to send the user a message to his email address whenever there is a
new status update, error message, or other reporting information. How will you configure the email
settings for an application?
What is the minimum permission required in order to access the Project Server Reporting Database for the Cube
What is the minimum permission required in order to access the Project Server Reporting Database
for the Cube Generation Service for the SQL Server Analysis Services account?
Choose and reorder the steps to create a Project Server service application.
What will happen to a project if a project manager elects to do resource leveling?
What will happen to a project if a project manager elects to do resource leveling?
What is the process of adding resources to a project called?
You are examining the Total Slack and Critical columns to review the overall program performance of
your master project. You believe that one of your projects is slipping on its schedule and you would
like to add additional resources to effort-driven activities to help the project finish on time. What is
the process of adding resources to a project called?
What is the most likely reason why the media was overwritten even though Holly used a password on the backup t
Holly is the Microsoft Project Server administrator and she has completed a full backup of her
Microsoft SQL Server database. Holly has added a media set password to the backup tape. Holly later
learns that someone has overwritten the media although she used a password on the backup tape.
What is the most likely reason why the media was overwritten even though Holly used a password
on the backup tape?