You have configured Resource Governor with three resource pools.

You

have configured Resource Governor with three resource pools.

You have assigned the first resource pool a minimum CPU and memory value of 20%.

You have assigned the second resource pool a minimum CPU and memory value of 30%.

You want to assign maximum C

PU and memory values to the third resource pool.

What is the maximum CPU and memory value you can assign to this resource pool?

A. 30%

B. 50%

C. 70%

D. 100%

The maximum resource value assigned to the third pool is 100%; the sum of the minimum

resource values assigned to the other pools is 50%.