As part of a risk analysis, technical risks are analyzed. Which TWO factors influence technical
risk?

A.
Complexity of technology
B.
Frequency of use of the affected failure
C.
Interfacing and integration issues
D.
Damage to image
E.
Lack of reasonable workaround
Explanation:
Correct answer is AC