Which of the following would be appropriate as a measure of test coverage?

Topic 10, Scenario 10, V3 “Online Application”
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has proposed an
in-house development with the use of a Rapid Application Development (RAO) approach.
***************************************

The business has asked for a weekly progress report. Which of the following would be appropriate
as a measure of test coverage?

PrepAway - Latest Free Exam Questions & Answers

A.
Percentage of business requirements exercised

B.
Percentage of planned hours worked this week

C.
Percentage of countries that have test scenarios

D.
Percentage of test iterations completed

Explanation:

One Comment on “Which of the following would be appropriate as a measure of test coverage?


Leave a Reply