Which of the following review types would be recommended at the start of each Sprint, for the reason

Topic 2, Case Study # 2 Scenario
Your organization is a large media services corporation (MSC).
MSC uses Agile development, within a Scrum framework. Here, the iterations are referred to as
Sprints.
For each Sprint, a set of user-stories is defined, built, and tested. The user-stories are typically 1-2 lines long, indicating what the customer wants the system to do.
MSC is in the process of updating its website to meet the recently introduced accessibility rules for
websites. Accessibility means the availability of a system suitable to members of the public with,
for example, visual or hearing difficulties.
It has been decided to start with two requirements, as its first 2 Sprints:
1) Presentation of content with clear headings, short sentences, text versions always available.
2) Consistent navigation through the website.
You are the test manager and there are four developers and two testers. You have all worked
together previously, and are very experienced in MSCs products. Although the accessibility rules
are new to you and the team, you have all attended a workshop where they were explained.
**************************************

Which of the following review types would be recommended at the start of each Sprint, for the
reason given?

A.
An inspection, to find errors in the user-stories.

B.
A management review, to check that the user-stories will accurately reflect the rules for
accessibility.

C.
A walkthrough of the set of user-stories, to ensure that the developers and testers understand
what is to be built.

D.
A technical review of the test plan, to ensure that the developers are aware that they must
produce good quality code.

Explanation: