During development, testing, and maintenance of the continuity plan, a high degree of interaction and communications is crucial to the process. Why?

A.
This is a regulatory requirement of the process.

B.
The more people who talk about it and are involved, the more awareness will increase.

C.
This is not crucial to the plan and should not be interactive because it will most likely affect operations.

D.
Management will more likely support it.

Explanation:
B: Communication not only spreads awareness of these plans and their contents, but also allows more people to discuss the possible threats and solutions, which may lead to ideas that the original team did not consider.