Which plan details the steps required to restore normal business operations after a recovering from

Which plan details the steps required to restore normal business operations after a recovering from a disruptive event?

A.
Business Continuity Planning (BCP)

B.
Business Resumption Planning (BRP)

C.
Continuity of Operations Plan (COOP)

D.
Occupant Emergency Plan (OEP)

Explanation:
Answer B is correct; Business Resumption Planning details the steps required to restore normal business operations after a recovering from a disruptive event.

Incorrect Answers and Explanations: A, C, and D: Answers A, C, and D are incorrect. Business Continuity Planning develops a long-term plan to ensure the continuity of business operations. The Continuity of Operations Plan describes the procedures required to maintain operations during a disaster. The Occupant Emergency Plan provides the response procedures for occupants of a facility in the event a situation poses a threat to the health and safety of personnel, the environment, or property.