Which of thefollowing will allow Tim to focus risk management efforts on identified risks?

Tim is responsible for contingency planning at his company. Which of the
following will allow Tim to focus risk management efforts on identified risks?

A.
A risk assessment

B.
Residual risks

C.
Security controls

D.
Business units

Explanation:
The risk assessment is critical because it enables the person
responsible for contingency planning to focus risk management efforts and resources
in a prioritized manner only on the identified risks.