ISC Exam Questions

Which of the following would be the most serious risk where a systems development life cycle methodo

Which of the following would be the most serious risk where a systems development life cycle
methodology is inadequate?

A.
The project will be completed late

B.
The project will exceed the cost estimates

C.
The project will be incompatible with existing systems

D.
The project will fail to meet business and user needs