ISC Exam Questions

Which of the following tasks describes the processes required to ensure that the project includes al

Which of the following tasks describes the processes required to ensure that the project includes
all the work required, and only the work required, to complete the project successfully

A.
Identify Roles and Responsibilities

B.
Develop Project Schedule

C.
Identify Resources and Availability

D.
Estimate project scope