ISC Exam Questions

Which of the following risk responses delineates that the project plan will not be changed to deal w

Which of the following risk responses delineates that the project plan will not be changed to
deal with the risk?

A.
Mitigation

B.
Exploitation

C.
Acceptance

D.
Transference