Which of the following risk responses delineates that the project plan will not be changed to deal w seenagape 8 years ago Which of the following risk responses delineates that the project plan will not be changed todeal with the risk? A. Mitigation B. Exploitation C. Acceptance D. Transference ← Previous question Next question →