Which of the following is NOT one of the five disaster recovery plan testing
types?
A.
Mobile
B.
Checklist
C.
Full Interruption
D.
Simulation
Explanation:
The correct answer is mobile. The other three are proper examples
of elements of the five disaster recovery plan testing types.