ISC Exam Questions

What portion of the project will you most likely use for probability distributions?

Ned is the project manager of the HNN project for your company. Ned has asked you to
help him complete some probability distributions for his project. What portion of the project
will you most likely use for probability distributions?

A.
Bias towards risk in new resources

B.
Risk probabilityand impact matrixes

C.
Uncertainty in values such as duration of schedule activities

D.
Risk identification