What is one of the first steps in developing a business continuity plan?

What is one of the first steps in developing a business continuity plan?

A.
Identify backup solution.

B.
Decide whether the company needs to perform a walk-through, parallel, or simulation test.

C.
Perform a business impact analysis.

D.
Develop a business resumption plan.

Explanation:
C: A business impact analysis includes identifying critical systems and functions of a company and interviewing representatives from each department. Once managements support is solidified, a business impact analysis needs to be performed to identify the threats the company faces and the potential costs of these threats.